| Banwell Road (From McHugh Street to McNorton Street) |
10/4/2021 |
10/29/2021 |
Monday, October 04, 2021 to Friday, October 29, 2021 |
The Banwell Road southbound left thru lane at the McHugh Street/McNorton Street intersection will be closed for approximately one (1) month for the construction of a new left turn lane and median work. Local traffic will be permitted only. From October 4, 2021 to October 29, 2021 - weather permitting. |
Paul Mourad, P. Eng. (519) 562-2448 |
Elmara Construction Co Limited |
Complete |
road |
Complete All |
10/04/2021 00:00:00 |
10/29/2021 00:00:00 |
| Bernard Road (From Tecumseh Road East to Guy Street) |
5/25/2021 |
10/1/2021 |
Tuesday, May 25, 2021 to Friday, October 01, 2021 |
Bernard Road from Tecumseh Road East to Guy Street will be closed for approximately 5 months for sewer, pavement, watermain and street lighting rehabilitation. Local traffic will be permitted only. The westbound curb lane and eastbound left turn lane on Tecumseh Road East will be closed as needed.
|
Joe Bressan, Engineering 1,Operations (519) 255-6100 x6890 |
Sterling Ridge Infrastructure Inc. |
Complete |
road,sewer,sidewalk,watermain |
Complete All |
05/25/2021 00:00:00 |
10/01/2021 00:00:00 |
| Byng Road (From Seymour Boulevard to Lappan Avenue) |
6/21/2021 |
8/27/2021 |
Monday, June 21, 2021 to Friday, August 27, 2021 |
As part of an ongoing infrastructure renewal program, the Windsor Utilities Commission (WUC) will be installing a new 200mm dia. PVC watermain on Byng Road from Seymour Boulevard to Lappan Avenue.
Byng Pre-Construction Notification.pdf
|
Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 |
Major Construction (2010) Ltd. |
Complete |
watermain |
Complete All |
06/21/2021 00:00:00 |
08/27/2021 00:00:00 |
| Caban/Dougall Intersection Closure (From Cabana Road to Dougall Avenue) |
10/22/2021 |
10/27/2021 |
Friday, October 22, 2021 to Wednesday, October 27, 2021 |
As part of the Cabana Road Corridor Improvements Phase 3, the intersection of Cabana Road and Dougall Avenue will be completely closed to traffic for road reconstruction and traffic signal work. Access for emergency vehicles will be maintained. A noise by-law exemption was approved by City Council to allow for the accelerated completion of the work. Detour signage will be in place. From 8:00pm on Friday, October 22 until 8:00pm Wednesday, October 27, 2021. (weather permitting). |
Jane He, P. Eng., Engineering (519) 255-6257 x6358 |
Amico Infrastructures Inc. / City of Windsor |
Complete |
road |
Complete All |
10/22/2021 00:00:00 |
10/27/2021 00:00:00 |
| Cabana Corridor Improvements Phase 3 (From Dougall Avenue to Northway Avenue) |
4/19/2021 |
12/31/2021 |
Monday, April 19, 2021 to Friday, December 31, 2021 |
Watch for lane restrictions and construction crews along Cabana Road West between Dougall Avenue and Northway Avenue. New infrastructure work is set to get underway, possibly this week, and while some road closures may be needed from time to time, through traffic is expected to be maintained for the most part.
cabana.pdf
|
Jane He, P. Eng., Engineering (519) 255-6257 x6358 |
Amico Infrastructures |
Complete |
road |
Complete All |
04/19/2021 00:00:00 |
12/31/2021 00:00:00 |
| Cabana Road Improvements Phase 3 Road Closures (From Dominion Boulevard to McKay Avenue) |
8/3/2021 |
9/6/2021 |
Tuesday, August 03, 2021 to Monday, September 06, 2021 |
As part of the Cabana Road Corridor Improvements - Phase 3, Dominion Boulevard and McKay Avenue will be closed between Roselawn Drive and Cabana Road. Local traffic only. From Tuesday, August 3, 2021, until approximately Labour Day. |
Jane He, P. Eng., Engineering (519) 255-6257 x6358 |
Amico Infrastructures Inc. |
Complete |
road |
Complete All |
08/03/2021 00:00:00 |
09/06/2021 00:00:00 |
| Cabana Road West (From Dougall Avenue to Howard Avenue) |
4/26/2021 |
5/28/2021 |
Monday, April 26, 2021 to Friday, May 28, 2021 |
Cabana Road West will have lane restrictions between Dougall Avenue and Howard Avenue for sewer relining, boulevard restoration and surface asphalt paving work. Detour signage will be in place.
Dougall Avenue north of Cabana Road will have a one-day lane restriction as a result of this work on Monday, April 26, 2021.
|
Jane He, P. Eng., Engineering (519) 984-2235 |
SheaRock Construction Group Inc. |
Complete |
road,sewer |
Complete All |
04/26/2021 00:00:00 |
05/28/2021 00:00:00 |
| Cameron Avenue (From Riverside Drive West to Wyandotte Street West) |
3/25/2021 |
7/5/2021 |
Thursday, March 25, 2021 to Monday, July 05, 2021 |
Cameron Avenue from Riverside Drive West to Wyandotte Street West will be closed for approximately 2 months for the reconstruction of watermain and milling and paving of existing roadway. The roadway will be closed (local traffic only) for the duration of the project.
Cameron- Public Works Construction Notice.pdf
|
Michael Cappucci, P. Eng. Contracts Coordinator (519) 255-61000 x4234 |
Sterling Ridge Group Inc. |
Complete |
watermain,road |
Complete All |
03/25/2021 00:00:00 |
07/05/2021 00:00:00 |
| Campbell Avenue (From Riverside Drive West to Tecumseh Road West) |
6/28/2021 |
10/22/2021 |
Monday, June 28, 2021 to Friday, October 22, 2021 |
The Windsor Utilities Commission will be reconstructing the watermains on Campbell Avenue from Riverside Drive West to Tecumseh Road West (Ward 2).
Phase 1 - Riverside Drive West to University Avenue West
Phase 2 - University Avenue West to Wyandotte Street West
Phase 3 - Wyandotte Street West to ETR
Phase 4 - College Avenue to Tecumseh Road West
2021-019 Campbell PH1 Pre-Construction Notification.pdf
|
Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 |
Major Construction (2010) Ltd. |
Complete |
watermain |
Complete All |
06/28/2021 00:00:00 |
10/22/2021 00:00:00 |
| Campbell Avenue (From Riverside Drive West to Tecumseh Road West) |
8/24/2021 |
11/12/2021 |
Tuesday, August 24, 2021 to Friday, November 12, 2021 |
The Windsor Utilities Commission will be reconstructing the watermain on Campbell Avenue between Riverside Drive West and Tecumseh Road West (Ward 2).
Campbell PH3 Pre-Construction Notification.pdf
|
Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 |
Major Construction (2010) Ltd. |
Complete |
watermain |
Complete All |
08/24/2021 00:00:00 |
11/12/2021 00:00:00 |
| Campbell Avenue (From Riverside Drive West to Tecumseh Road West) |
9/15/2021 |
12/24/2021 |
Wednesday, September 15, 2021 to Friday, December 24, 2021 |
The Windsor Utilities Commission will be reconstructing the watermain on Campbell Avenue from Riverside Drive West to Tecumseh Road West (Ward 2).
Campbell PH4 Pre-Construction Notification.pdf
|
Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 |
Major Construction (2010) Ltd. |
Complete |
watermain |
Complete All |
09/15/2021 00:00:00 |
12/24/2021 00:00:00 |
| Central Avenue (From Central Avenue to E.C. Row Expressway) |
10/18/2021 |
11/7/2021 |
Monday, October 18, 2021 to Sunday, November 07, 2021 |
Southbound Central Avenue will be reduced to one lane leading to the Central Avenue Overpass, over the E.C. Row Expressway, starting on Monday October 18, 2021. This is the first of 3 phases of bridgework that will impact drivers between October 18 and November 7, 2021. Dates will be released for each stage as they draw nearer, and the work will generally include:
Stage 1 - Southbound Central Avenue reduced to one lane.
Stage 2 - Closure of entire structure for one weekend for asphalt resurfacing and line painting.
Stage 3 - Nightly closure of structure from 7:00pm to 5:00am, reopened for daytime traffic.
Detours will be posted for full closures and construction notices issued as work progresses. |
Michael Cappucci, P. Eng. Contracts Coordinator (519) 255-6326 |
Front Construction Industries Inc. |
Complete |
road,bridge |
Complete All |
10/18/2021 00:00:00 |
11/07/2021 00:00:00 |
| Crawford Avenue, Riverside Drive West, Oak Street (From see description to see description) |
3/1/2021 |
6/1/2021 |
Monday, March 01, 2021 to Tuesday, June 01, 2021 |
The Windsor Utilities Commission will be reconstructing the watermains on:
Crawford Avenue - Wyandotte Street West to Riverside Drive West
Riverside Drive West - Elm Avenue to Crawford Avenue
Oak Street - University Avenue West to Riverside Drive West
WUC Contract 2020-030 Pre-Construction Letter.pdf
|
Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 |
D'Amore Construction |
Complete |
watermain |
Complete All |
03/01/2021 00:00:00 |
06/01/2021 00:00:00 |
| Curry and McKay Avenue (From Grove Avenue to Adanac Avenue) |
3/8/2021 |
6/15/2021 |
Monday, March 08, 2021 to Tuesday, June 15, 2021 |
Curry Avenue and McKay Avenue will be closed between Grove Avenue and Adanac Avenue for sewer, watermain and road rehabilitation. Sidewalk and Boulevard restoration work will be done on Adanac Avenue between Campbell Avenue and Adanac Avenue.
|
Amandeep Bains, P. Eng. Engineer II (519) 816-4061 |
D'Amore Construction (2000) Ltd. |
Complete |
road,sewer,sidewalk,watermain,bridge |
Complete All |
03/08/2021 00:00:00 |
06/15/2021 00:00:00 |
| Curry Avenue (From Norfolk Street to Richardie Boulevard) |
10/4/2021 |
11/30/2021 |
Monday, October 04, 2021 to Tuesday, November 30, 2021 |
Curry Avenue from Norfolk Street to Richardie Boulevard will be closed for storm sewer, road reconstruction and local improvement.
|
June Liu-Vajko, Tech III Design and Development Engineering (519) 818-2409 |
Coco Paving Inc. |
Complete |
sewer,road |
Complete All |
10/04/2021 00:00:00 |
11/30/2021 00:00:00 |
| Eastlawn Avenue (From Wyandotte Street East to Edgar Street) |
9/8/2021 |
3/31/2022 |
Wednesday, September 08, 2021 to Thursday, March 31, 2022 |
Eastlawn Avenue from Wyandotte Street East to Edgar Street will be closed until approximately March of 2022 for sewer, pavement, watermain, sidewalk and streetlighting rehabilitation. Local Traffic only.
|
Andrew Dowie, P. Eng., (519) 255-6257 x6490 |
Sterling Ridge Infrastructure Inc. |
Current |
road,sewer,sidewalk,watermain |
Current All |
09/08/2021 00:00:00 |
03/31/2022 00:00:00 |
| E.C. Row Expressway (From E.C. Row Expressway to E.C. Row Expressway) |
12/14/2021 |
12/14/2021 |
Tuesday, December 14, 2021 |
E.C. Row Expressway will have lane restrictions in the following locations for guardrail repairs.
- Westbound between Banwell Road and Lauzon Parkway
- Eastbound between Howard Avenue and Walker Road
- Eastbound between Central Avenue and Jefferson Boulevard
Please slow down and use caution in the construction zones.
From 9:00am to 5:00pm on Tuesday, December 14, 2021. |
Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 |
Royal Fence |
Complete |
road |
Complete All |
12/14/2021 00:00:00 |
12/14/2021 00:00:00 |
| E.C. Row Expressway Ramp and Lane Closures (From Lauzon Parkway to Jefferson Boulevard) |
3/9/2021 |
3/9/2021 |
Tuesday, March 09, 2021 |
Ramp and Lane closures on E.C. Row Expressway between Jefferson Boulevard and Lauzon Parkway for guardrail repairs will affect traffic flow.
Closure of eastbound on-ramp at Lauzon Parkway, 9 a.m. to 12 p.m.
Closure of eastbound off-ramp at Lauzon Parkway and northbound lane restrictions, 12 p.m. to 2 p.m.
Westbound lane restrictions between Lauzon Parkway and Jefferson Boulevard, 12 p.m. to 3 p.m. |
Michael Cappucci, Contracts Coordinator 519-255-6326 |
Royal Fence |
Complete |
None. |
Complete All |
03/09/2021 00:00:00 |
03/09/2021 00:00:00 |
| Ford Boulevard and South National Street (From Ford Boulevard to South National Street) |
11/15/2021 |
12/17/2021 |
Monday, November 15, 2021 to Friday, December 17, 2021 |
The Windsor Utilities Commission will be resconstructing the watermains on Ford Boulevard from South National Street to Reginald Street and on South National Street from Polonia Park Place to Ford Boulevard.
WUC Contract 2021-027 Pre-Construction Letter Ford.pdf
|
Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 |
D'Amore Construction (2000) Ltd. |
Complete |
watermain |
Complete All |
11/15/2021 00:00:00 |
12/17/2021 00:00:00 |
| Gladstone Avenue and Ypres Avenue (From Gladstone Avenue to Ypres Avenue) |
6/9/2021 |
11/30/2021 |
Wednesday, June 09, 2021 to Tuesday, November 30, 2021 |
Gladstone Avenue from Tecumseh Road East to Ypres Avenue as well as Ypres Avenue from Forest Avenue to Walker Road will be under road and watermain construction for approximately 5 months. Gladstone Avenue will be closed and Ypres Avenue will be partially closed (westbound) for the duration of construction to local traffic only. Travellers should expect long delays and avoid area if possible. To complete the project as fast as possible, construction will occur simultaneously between the two streets (when possible).
|
Michael Cappucci, P. Eng. Contracts Coordinator (519) 255-61000 x4234 |
Sterling Ridge Group Inc. |
Complete |
road,watermain |
Complete All |
06/09/2021 00:00:00 |
11/30/2021 00:00:00 |
| Huron Church Road (From Tecumseh Road West to College Avenue) |
4/6/2021 |
8/15/2021 |
Tuesday, April 06, 2021 to Sunday, August 15, 2021 |
Huron Church Road will have lane(s) closed between Tecumseh Road West and College Avevue for the reconstruction of the road and watermain. Please follow posted detour signs. Expect delays.
Huron Church Road will continue to have lane restrictions between Tecumseh Road West and College Avenue for final electrical, signal and landscaping work to complete the construction project. Ongoing until Monday, September 6, 2021 (weather permitting).
Additional Improvements Announced for Huron Church Road.pdf
|
Michael Cappucci, P. Eng. Contracts Coordinator (519) 255-6100 x4234 |
Pieracon |
Complete |
road,watermain |
Complete All |
04/06/2021 00:00:00 |
08/15/2021 00:00:00 |
| Kildare Road (From Wyandotte Street East to Assumption Street) |
8/9/2021 |
9/17/2021 |
Monday, August 09, 2021 to Friday, September 17, 2021 |
The Windsor Utilities Commission will be reconstructing the watermains on: Kildare Road from Wyandotte Street East to Assumption Street (Ward 4).
Kildare Pre-Construction Notification.pdf
|
Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 |
Major Construction (2010) Ltd. |
Complete |
watermain |
Complete All |
08/09/2021 00:00:00 |
09/17/2021 00:00:00 |
| Labelle Street (From Dominion Boulevard to Rockwell Boulevard) |
4/26/2021 |
6/25/2021 |
Monday, April 26, 2021 to Friday, June 25, 2021 |
Labelle Street from Dominion Boulevard to Rockwell Boulevard will be closed for approximately 1 month for road rehabilitation. The road will be closed (local traffic only) for the duration of the project.
|
Michael Cappucci, P. Eng. Contracts Coordinator (519) 255-61000 x4234 |
D'Amore Construction (2000) Ltd. |
Complete |
road |
Complete All |
04/26/2021 00:00:00 |
06/25/2021 00:00:00 |
| Lauzon Parkway (From Tecumseh Road East to Hawthorne Drive) |
6/7/2021 |
10/1/2021 |
Monday, June 07, 2021 to Friday, October 01, 2021 |
Lauzon Parkway from Tecumseh Road East to Hawthorne Drive will be partially closed for approximately 4 months for the reconstruction of travel lanes, new sidewalk and multi-use trail. The roadway will be reduced to one lane in the southbound direction and one lane in the northbound direction for the duration of the project. Road users should expect delays. Access to all businesses remain open. From June 7 to October 1, 2021 (weather permitting).
|
Michael Cappucci, P. Eng. Contracts Coordinator (519) 255-61000 x4234 |
SheaRock Construction Group Inc. |
Complete |
road,sidewalk |
Complete All |
06/07/2021 00:00:00 |
10/01/2021 00:00:00 |
| Mark Avenue (From Campbell Avenue to Algonquin Street) |
9/13/2021 |
12/22/2021 |
Monday, September 13, 2021 to Wednesday, December 22, 2021 |
Mark Avenue from Campbell Avenue to Algonquin Street will be closed for approximately 4 months for sewer, pavement and watermain rehabilitation. Local traffic will be permitted only. The southbound lane of Campbell at Mark Avenue will be closed as needed.
|
Joe Bressan, Engineering 1,Operations (519) 255-6100 x6890 |
D'Amore Construction (2000) Inc. |
Complete |
road,sewer,watermain |
Complete All |
09/13/2021 00:00:00 |
12/22/2021 00:00:00 |
| North Talbot Road (From Howard Avenue to Southwood Lakes Boulevard) |
11/29/2021 |
12/3/2021 |
Monday, November 29, 2021 to Friday, December 03, 2021 |
Installation of water services on North Talbot Road from Howard Avenue to east of Southwood Lakes Boulevard. Expect some delays. |
Paul Mourad, P. Eng. (519) 562-2448 |
SheaRock Construction Group Inc. |
Complete |
watermain |
Complete All |
11/29/2021 00:00:00 |
12/03/2021 00:00:00 |
| Ojibway Parkway (From Sprucewood Avenue to GN Booth Drive) |
3/29/2021 |
9/30/2021 |
Monday, March 29, 2021 to Thursday, September 30, 2021 |
Southbound Ojibway Parkway will have partial lane restrictions intermittently between Sprucewood Avenue and GN Booth Drive for rehabilitation of the sanitary trunk sewer. Work will primarily take place on the shoulder of the roadway, but restrictions may occasionally be required.
|
Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 |
Clean Water Works Inc. |
Complete |
sewer |
Complete All |
03/29/2021 00:00:00 |
09/30/2021 00:00:00 |
| Olive Road (From Milloy Street to Tecumseh Road East) |
5/17/2021 |
10/30/2021 |
Monday, May 17, 2021 to Saturday, October 30, 2021 |
Olive Road from Milloy Street to Tecumseh Road East will be closed for approximately four months for the rehabilitation of sanitary and storm sewers, pavement, watermain and street lighting. Local traffic will be permitted only.
|
Tiffany Pocock, P. Eng. (519) 259-8567 |
D'Amore Construction (2000) Ltd. |
Complete |
road,sewer,sidewalk,watermain |
Complete All |
05/17/2021 00:00:00 |
10/30/2021 00:00:00 |
| Parent Avenue (From Erie Street East to Giles Boulevard West) |
3/8/2021 |
4/30/2021 |
Monday, March 08, 2021 to Friday, April 30, 2021 |
The Windsor Utilities Commission will be reconstructing the watermains on Parent Avenue from Erie Street East to Giles Boulevard West (Ward 4).
WUC Contract 2020-032 Parent - Giles to Erie.pdf
|
Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 |
Coco Paving |
Complete |
watermain |
Complete All |
03/08/2021 00:00:00 |
04/30/2021 00:00:00 |
| Parkside Court (From Beals Street West to 1548 Parkside Court) |
11/16/2020 |
12/7/2020 |
Monday, November 16, 2020 to Monday, December 07, 2020 |
Parkside Court will be closed from Beals Street West to 1548 Parkside Court for Watermain Reconstruction.
|
Spencer Johnston, WUC 519-251-7300 x 609 |
To be determined.
|
Complete |
watermain |
Complete All |
11/16/2020 00:00:00 |
12/07/2020 00:00:00 |
| Provincial/Division Corridor Improvements Phase 2 (From Lowe's / Monarch Basics to Legacy Park Drive) |
10/20/2020 |
11/26/2021 |
Tuesday, October 20, 2020 to Friday, November 26, 2021 |
Provincial Road from Lowe's / Monach Basics intersection to Legacy Park Drive is fully OPEN by December 18, 2020. Construction continues on 6th CONCESSION DRAIN and NORTH ROSELAND PUMP STATION in CAPTAIN JOHN WILSON PARK.
|
Jane He, P. Eng., Engineering (519) 255-6257 x6358 |
J&J Lepera Infrastructure |
Complete |
watermain |
Complete All |
10/20/2020 00:00:00 |
11/26/2021 00:00:00 |
| Randolph Avenue (From Cleary Street to Northwood Street) |
9/13/2021 |
12/17/2021 |
Monday, September 13, 2021 to Friday, December 17, 2021 |
Randolph Avenue from Cleary Street to Northwood Street will be closed for storm sewer, pavement, watermain streetlighting rehabilitation and local improvement work. Local traffic only.
|
Sarah Meneses, P. Eng. (519) 255-6100 x6336 |
J.C.S. Construction Inc. |
Complete |
road,sewer,watermain |
Complete All |
09/13/2021 00:00:00 |
12/17/2021 00:00:00 |
| Rankin Avenue (From Union Street to Wyandotte Street West) |
9/27/2021 |
12/10/2021 |
Monday, September 27, 2021 to Friday, December 10, 2021 |
Rankin Avenue from Union Street to Wyandotte Street West will be closed for approximately 2 months for sewer, pavement and street lighting rehabilitation. Local traffic will be permitted only.
|
Michael Todd, P. Eng. (519) 255-6100 x6407 |
D'Amore Construction (2000) Ltd. |
Complete |
road,sewer |
Complete All |
09/27/2021 00:00:00 |
12/10/2021 00:00:00 |
| Rhodes Drive (From Deziel Drive to Wheelton Drive) |
12/14/2021 |
12/15/2021 |
Tuesday, December 14, 2021 to Wednesday, December 15, 2021 |
Rhodes Drive will have lane restrictions between Deziel Drive and Wheelton Drive for road repairs. Please slow down and use caution in the construction zone. Flag persons will be on hand. |
Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 |
Diponti Paving |
Complete |
road |
Complete All |
12/14/2021 00:00:00 |
12/15/2021 00:00:00 |
| Riverside Drive East (From Little River Drain to East of Riverdale) |
7/5/2021 |
10/15/2021 |
Monday, July 05, 2021 to Friday, October 15, 2021 |
Riverside Drive East will be closed for structure rehabilitation work on the bridge over Little River Drain (east of Riverdale).
|
Zoran Savic (519) 255-6326 ext. 4231 zsavic@citywindsor.ca |
Front Construction Ltd. |
Complete |
bridge |
Complete All |
07/05/2021 00:00:00 |
10/15/2021 00:00:00 |
| Tecumseh Road East (From Forest Glade Drive to Clover Avenue) |
3/10/2021 8:00 AM |
3/11/2021 5:00 PM |
Wednesday, March 10, 2021 8:00 AM to Thursday, March 11, 2021 5:00 PM |
Tecumseh Road East currently has eastbound lane restrictions between Forest Glade and Clover Avenue for catch basin repairs. |
Roberta Harrison, Maintinance Corrdinator, (519) 266-65660 x4241 |
DanRuss |
Complete |
sewer |
Complete All |
03/10/2021 08:00:00 |
03/11/2021 17:00:00 |
| Tecumseh Road East (From Walker Road to Drouillard Road) |
7/8/2021 |
9/8/2021 |
Thursday, July 08, 2021 to Wednesday, September 08, 2021 |
Westbound Tecumseh Road from Drouillard Road to Walker Road will be single lane traffic for 2 months for the road and watermain rehabilitation. Travellers should expect long delays. |
Michael Cappucci, P. Eng. Contracts Coordinator (519) 255-61000 x4234 |
Sherway Contracting (Windsor) Limited |
Complete |
watermain,road |
Complete All |
07/08/2021 00:00:00 |
09/08/2021 00:00:00 |
| Westminster Boulevard (From Wyandotte Street East to CNR rail tracks) |
10/18/2021 |
12/10/2021 |
Monday, October 18, 2021 to Friday, December 10, 2021 |
As part of an ongoing infrastructure renewal program, the Windsor Utilities Commission (WUC) will be installing a new 200mm PVC watermain on Westminster Boulevard from Wyandotte Street East to CNR rail tracks by horizontal directional drilling method. Work is scheduled to begin the week of October 18, 2021. The project should take approximately 8 weeks to complete. Project timing is weather dependant. Tree trimming will also occur in advance by a certified sub-contractor.
|
Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 |
D'Amore Construction (2000) Ltd. |
Complete |
watermain |
Complete All |
10/18/2021 00:00:00 |
12/10/2021 00:00:00 |
| Ypres Avenue (From Forest Avenue to Walker Road) |
10/18/2021 |
11/26/2021 |
Monday, October 18, 2021 to Friday, November 26, 2021 |
Eastbound Ypres Avenue will be closed between Forest Avenue and Walker Road for road construction. From Monday, October 18 to Friday, November 26, 2021. |
Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 |
Sterling Ridge Infrastructure |
Complete |
road |
Complete All |
10/18/2021 00:00:00 |
11/26/2021 00:00:00 |