Construction and Detours

This Construction and Detours Database is used for City of Windsor and Windsor Utilities Commission (WUC) projects only. If the project you are looking for is not listed below, please visit Municipal 511.  

Using the Construction and Detours Database

You can search and sort projects by several convenient methods:

  • Filter according to time, choosing from All, Current, Planned or Complete.
  • Keyword Search by street name, project type or any word that may appear in the entry.
  • By column, you can click the heading of any column to sort by that category in either ascending or descending order.​
  • By page, you can move from page to page (ten entries per page) using the buttons at the bottom.

Expand the listing to learn more by clicking the plus + symbol and close it by clicking the minus - symbol.

Street Name Start Date End Date Estimated Duration Description Contact Contractor Status Keywords Filterable Status Sortable Start Date Sortable End Date
Street Name Start Date End Date Estimated Duration Description Contact Contractor Status Keywords Filterable Status Sortable Start Date Sortable End Date
Alice Street (From Labadie Road to Westcott Road) 11/10/2022 11/11/2022 Thursday, November 10, 2022 to Friday, November 11, 2022

​Alice Street will be closed between Labadie Road and Westcott Road for mill and pave work. Local traffic only. On Thursday, November 10 and Friday, November 11, 2022.

Daryl Lundy, A.Sc.T., Contracts Supervisor (519) 255-6560 x4330 Coco Paving Complete road Complete All 11/10/2022 00:00:00 11/11/2022 00:00:00
Argyle Road, Richmond Street and Devonshire Road (From see description to see description) 4/4/2022 7/22/2022 Monday, April 04, 2022 to Friday, July 22, 2022

​The Windsor Utilities Commission will be reconstructing the watermains on:

Argyle Road - Richmond Street to Ottawa Street (Ward 4)

Richmond Street - Argyle Road to Devonshire Road (Ward 4)

Devonshire Road - Richmond Street to Willistead Crescent (Ward 4)

WUC Contract 2022-002 Pre-Construction Letter DAR.pdfWUC Contract 2022-002 Pre-Construction Letter DAR.pdf

Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 D'Amore Construction (2000) Ltd. Complete watermain Complete All 04/04/2022 00:00:00 07/22/2022 00:00:00
Argyle Road/Niagara Street (From see description to see description) 5/16/2022 8/19/2022 Monday, May 16, 2022 to Friday, August 19, 2022

​The Windsor Utilities Commission will be reconstructing the watermains on:

Argyle Road from Wyandotte Street East to Niagara Street (Ward 4)

Niagara Street from Kildare Road to Walker Road (Ward 4)

WUC Contract 2022-002 Pre-Construction Letter Argyle Niagara.pdfWUC Contract 2022-002 Pre-Construction Letter Argyle Niagara.pdf

Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 D'Amore Construction (2000) Ltd. Complete watermain,bridge Complete All 05/16/2022 00:00:00 08/19/2022 00:00:00
Arthur Road (From Ontario Street to VIA Rail) 8/31/2022 11/30/2022 Wednesday, August 31, 2022 to Wednesday, November 30, 2022

​Arthur Road will be closed for storm and sanitary sewer, watermain and pavement rehabilitation from Ontario Street to VIA Rail. Local Traffic Only.

Sarah Meneses, P. Eng. (519) 255-6100 x6336 SheaRock Construction Group Inc. Current road,sewer,watermain Current All 08/31/2022 00:00:00 11/30/2022 00:00:00
Aubin Road and Reginald Street (From see description to see description) 7/18/2022 12/23/2022 Monday, July 18, 2022 to Friday, December 23, 2022

​Aubin Road from Seminole Street to Alice Street and Reginald Street from Aubin Road to Westcott Road will be closed for approximately five months for sewer, pavement, watermain and streetlighting rehabilitation. Local traffic will be permitted only. The westbound lane of Seminole Street will be shifted around the area of construction at the intersection of Aubin and Seminole as needed.

Joe Bressan, EIT Engineering 1, Operations (519) 255-6100 x6890 Sterling Ridge Infrastructure Inc. Current sewer,road,watermain Current All 07/18/2022 00:00:00 12/23/2022 00:00:00
Banwell Road (From Palmetto Street to Mulberry Drive/Wildwood Drive) 8/2/2022 6/30/2023 Tuesday, August 02, 2022 to Friday, June 30, 2023

​Installation of storm sewers, road widening (including trail and sidewalks), roundabout and streetlights on Banwell Road from Palmetto Street to Mulberry Drive/Wildwood Drive. Alternating traffic lanes. Local traffic only.

The southbound lane on Banwell Road between Palmetto Street and Mulberry/Wildwood Drive will be closed on Thursday, September 1 from 9:00am to 3:00pm and on Friday, September 2 from 9:00am to 2:00pm for streetlight work. Local traffic only.

As part of the Banwell Road improvements, Phase 2, the Wildwood Drive/Banwell Road intersection will be closed to traffic for sewer work. From 7:00am to 5:00pm on Monday, October 3 to Thursday, October 6, 2022.

Paul Mourad, P. Eng. (519) 255-6100 x6119 SheaRock Construction Group Inc. Current sewer,road,sidewalk Current All 08/02/2022 00:00:00 06/30/2023 00:00:00
Bernard Road (From Tecumseh Road East to Guy Street) 8/31/2022 9/2/2022 Wednesday, August 31, 2022 to Friday, September 02, 2022

​Bernard Road will be closed for surface asphalt placement from Tecumseh Road East to Guy Street. From Wednesday, August 31 to Friday, September 2, 2022 (weather permitting).

Charles Hartford Contracts Coordinator Operations (519) 255-6326 Coco Paving Complete road Complete All 08/31/2022 00:00:00 09/02/2022 00:00:00
Bernard Road Alley (From Tecumseh Road East to Francois Road) 8/8/2022 8/12/2022 Monday, August 08, 2022 to Friday, August 12, 2022

​East-West Alley between Bernard Road and the North-South Alley between Bernard Road and Francois Road, all north of Tecumseh Road East will be closed for approximately 1 week for relining rehabilitation.

Joe Bressan, EIT Engineering 1, Operations (519) 255-6100 x6890 Sterling Ridge Infrastructure Inc. Complete sewer Complete All 08/08/2022 00:00:00 08/12/2022 00:00:00
Byng Road (From see description to see description) 9/28/2022 10/5/2022 Wednesday, September 28, 2022 to Wednesday, October 05, 2022

​Byng Road will be closed between Lappan Avenue and Melinda Avenue, and Melinda Avenue will be closed between Byng Road and Turner Road for placement of surface asphalt. Local traffic only.

Daryl Lundy, A.Sc.T., Contracts Supervisor (519) 255-6560 x4330 Coco Paving Complete road Complete All 09/28/2022 00:00:00 10/05/2022 00:00:00
Cabana Corridor Improvements Phase 3 (From Dougall Avenue to Dominion Boulevard) 6/9/2022 12/20/2022 Thursday, June 09, 2022 to Tuesday, December 20, 2022

​Cabana Road West from Dougall Avenue to Dominion Boulevard will have isolated lane restrictions for boulevard restoration and surface asphalt pavement.

Jane He, P. Eng., Engineering (519) 255-6257 x6358 Amico Infrastructures Current road Current All 06/09/2022 00:00:00 12/20/2022 00:00:00
Cabana Road West - Phase 4 (From Northway Avenue to Dominion Boulevard) 6/7/2022 12/20/2022 Tuesday, June 07, 2022 to Tuesday, December 20, 2022

​Cabana Road West will have isolated lane restrictions between Northway Avenue and Dominion Boulevard for Enwin Utility Contract and the relocation of hydro lines.

Notice to Homeowner - Cabana Ph 4 - ENWIN.pdfNotice to Homeowner - Cabana Ph 4 - ENWIN.pdf

Jane He, P. Eng., Engineering (519) 255-6257 x6358 Enwin Utility/Black and McDonald Current road Current All 06/07/2022 00:00:00 12/20/2022 00:00:00
Campbell Avenue (From Riverside Drive West to Tecumseh Road West) 9/15/2021 12/24/2021 Wednesday, September 15, 2021 to Friday, December 24, 2021

​The Windsor Utilities Commission will be reconstructing the watermain on Campbell Avenue from Riverside Drive West to Tecumseh Road West (Ward 2).

Campbell PH4 Pre-Construction Notification.pdfCampbell PH4 Pre-Construction Notification.pdf

Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 Major Construction (2010) Ltd. Complete watermain Complete All 09/15/2021 00:00:00 12/24/2021 00:00:00
Casgrain Drive (From Bartlet Drive to Cousineau Road) 10/18/2022 10/20/2022 Tuesday, October 18, 2022 to Thursday, October 20, 2022

​Casgrain Drive will have lane restrictions between Bartlet Drive and Cousineau Road for mill and pave work. From 7:00am to 7:00pm on Tuesday, October 18 until Thursday, October 20, 2022.

CJ Hartford Contracts Coordinator Operations (519) 255-6560 x4234 Coco Paving Complete road Complete All 10/18/2022 00:00:00 10/20/2022 00:00:00
Curry Avenue (From Norfolk Street to Richardie Boulevard) 10/4/2021 11/30/2021 Monday, October 04, 2021 to Tuesday, November 30, 2021

Curry Avenue from Norfolk Street to Richardie Boulevard will be closed for storm sewer, road reconstruction and local improvement.

June Liu-Vajko, Tech III Design and Development Engineering (519) 818-2409 Coco Paving Inc. Complete sewer,road Complete All 10/04/2021 00:00:00 11/30/2021 00:00:00
Devonshire Road (From Richmond Street to Ontario Street) 3/25/2022 6/3/2022 Friday, March 25, 2022 to Friday, June 03, 2022

​The Windsor Utilities Commission will be reconstructing the watermains on Devonshire Road from Richmond Street to Ontario Street (Ward 4).

WUC Contract 2022-002 Pre-Construction Letter Devonshire.pdfWUC Contract 2022-002 Pre-Construction Letter Devonshire.pdf

Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 D'Amore Construction (2000) Ltd. Complete watermain,bridge Complete All 03/25/2022 00:00:00 06/03/2022 00:00:00
Dominion Boulevard (From Northwood Street to Labelle Street) 4/11/2022 8/3/2022 Monday, April 11, 2022 to Wednesday, August 03, 2022

Dominion Boulevard North and South Bound, from Northwood Street to Labelle Street will be down to a single lane in both directions for approximately 80 days for bridge rehabilitation.

Brian Rempel (519) 255-6560 x4333 Coco Paving Complete bridge Complete All 04/11/2022 00:00:00 08/03/2022 00:00:00
Dougall Avenue (From Ouellette Avenue to Eugenie Street West) 8/8/2022 12/16/2022 Monday, August 08, 2022 to Friday, December 16, 2022

​Dougall Avenue from Ouellette Avenue to Eugenie Street West will be closed for approximately 3 months for storm sewer, pavement, watermain and street lighting rehabilitation. Local traffic will be permitted only. The southbound lane of Dougall Avenue will be closed during working hours.

Patrick Muzyka, P. Eng. Technologist III (519) 255-6100 x6472 Sherway Contracting (Windsor) Limited Current road,sewer,watermain Current All 08/08/2022 00:00:00 12/16/2022 00:00:00
Dougall Avenue (From Ouellette Place to South Cameron Bouelvard) 10/14/2022 10/14/2022 Friday, October 14, 2022

​Southbound Dougall Avenue will have lane restrictions between Ouellette Place and South Cameron Boulevard for milling and paving work. From 6:00am to 6:00pm on Friday, October 14, 2022.

Daryl Lundy, A.Sc.T., Contracts Supervisor (519) 255-6560 x4330 Coco Paving Complete road Complete All 10/14/2022 00:00:00 10/14/2022 00:00:00
Dougall Avenue (From Nottingham Street to West Grand Boulevard) 11/15/2022 11/15/2022 Tuesday, November 15, 2022

​Northbound Dougall Avenue will have lane restrictions between Nottingham Street and West Grand Boulevard for road and sidewalk repairs.

Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 PieraCon Complete road,sidewalk Complete All 11/15/2022 00:00:00 11/15/2022 00:00:00
Dougall Avenue (From Nottingham Street to West Grand Boulevard) 11/16/2022 11/30/2022 Wednesday, November 16, 2022 to Wednesday, November 30, 2022

​Northbound Dougall Avenue will have lane restrictions between Nottingham Street and West Grand Boulevard for road and sidewalk repairs. From Wednesday, November 16 until Wednesday, November 30, 2022.

Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 PieraCon Current road,sidewalk Current All 11/16/2022 00:00:00 11/30/2022 00:00:00
Eastlawn Avenue (From Wyandotte Street East to Edgar Street) 3/24/2022 5/31/2022 Thursday, March 24, 2022 to Tuesday, May 31, 2022

Eastlawn Avenue from Wyandotte Street East to Edgar Street will be closed for approximately 2 months for sewer, pavement, watermain, sidewalk and streetlighting rehabilitation. Local Traffic only.

Andrew Dowie, P. Eng., (519) 255-6257 x6490 Sterling Ridge Infrastructure Inc. Complete road,sewer,sidewalk,watermain Complete All 03/24/2022 00:00:00 05/31/2022 00:00:00
E.C. Row Avenue East (From East of 9455 Anchor Drive to Banwell Road) 8/25/2022 12/30/2022 Thursday, August 25, 2022 to Friday, December 30, 2022

​Temporary Road closure on EC ROW Avenue East between East side of 9455 Anchor Drive and Banwell Road.  The closure is due to restore boulevard construction in this area. Proper pedestrian and traffic signs will be present.

Patrick Winters, Development Engineer, (519)255-6257 x6462 A-BM - Brian Conklin, Senior Project Manager Current road Current All 08/25/2022 00:00:00 12/30/2022 00:00:00
E.C. Row Expressway (From Huron Church Road to Howard Avenue) 4/13/2022 8/5/2022 Wednesday, April 13, 2022 to Friday, August 05, 2022

​E.C. Row Expressway will have lane restrictions in both directions between Huron Church Road and Howard Avenue for approximately 17 weeks for road reconstruction.

E.C. Row Expressway Eastbound On ramp at Dominion Boulevard and Off ramp at Dougall Avenue will be closed for approximately the next 50 days. From April 28 to July 25 - weather permitting.

E.C. Row Expressway Westbound On ramp at Dougall Avenue will have daily shoulder closures for approximately the next 14 days. May 11 to May 25 - weather permitting.

E.C. Row Expressway Eastbound OFF ramp at Dominion Boulevard will be CLOSED for approximately 4 hours (10:00am - 2:00pm) on Wednesday, May 25 - weather permitting.

CJ Hartford Contracts Coordinator Operations (519) 945-9971 x4234 Coco Paving Complete road Complete All 04/13/2022 00:00:00 08/05/2022 00:00:00
E.C. Row Expressway (From Lauzon Parkway to Banwell Road) 9/28/2022 9/29/2022 Wednesday, September 28, 2022 to Thursday, September 29, 2022

​The City of Windsor is continuing road repairs on the eastbound lanes of the E.C. Row Expressway.

The next closure will take place between Lauzon Parkway and Banwell Road from 11:00pm on Wednesday, September 28, until 5:30am on Thursday September 29, 2022. The Lauzon Parkway off-ramps will remain open.

The work is scheduled during overnight hours in an effort to inconvenience as few motorists as possible.

Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 Alite Spray Patching Complete road Complete All 09/28/2022 00:00:00 09/29/2022 00:00:00
E.C. Row Expressway (From see description to see description) 10/17/2022 10/28/2022 Monday, October 17, 2022 to Friday, October 28, 2022

​Drivers are asked to use extra caution on the E.C. Row Expressway this week and next, as City of Windsor Parks staff will be cutting grass starting on Monday, October 17, 2022.

Cutting will take place on the centre median, roadside shoulders and all on-and-off ramps.

Crews will begin at 6:30am and there will be rolling lane closures in effect for the cutting along shoulders and on/off ramps. The work will last until 4:30pm each day.

At the completion of shoulder work, crews will begin cutting the median starting at Huron Church Road and moving east towards Banwell Road.

Motorists are asked to use extra caution and slow down when seeing workers and traffic protection equipment on or near the roadways.

This work will last for approximately two weeks weather dependant.

Kyle Deslippe, Supervisor, Parks and Facilities (519) 819-4237 City of Windsor Parks staff Complete road Complete All 10/17/2022 00:00:00 10/28/2022 00:00:00
E.C. Row Expressway (From Dougall Avenue to Banwell Road) 11/4/2022 11/6/2022 Friday, November 04, 2022 to Sunday, November 06, 2022

​Line Painting will take place on the E.C. Row Expressway in the east and westbound lanes between Dougall Avenue and Banwell Road. Please allow room for the trucks at work, and avoid driving on any/all lane markings if possible. From 10:00pm Friday, November 4 until 6:00am Saturday November 5, 2022 and 8:00pm Saturday, November 5 until 6:00am Sunday, November 6, 2022.

Mike Gertsakis, Supervisor Signs and Markings (519) 796-4048 To be determined. Complete road Complete All 11/04/2022 00:00:00 11/06/2022 00:00:00
E.C. Row Expressway Off-Ramp (Walker Road) 11/1/2022 11/1/2022 Tuesday, November 01, 2022

​The eastbound E.C. Row Expressway off-ramp at Walker Road will have lane restrictions for sewer repairs. From 8:00am to 6:00pm on Tuesday, November 1, 2022.

Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 DanRuss Complete sewer Complete All 11/01/2022 00:00:00 11/01/2022 00:00:00
E.C. Row Expressway On-Ramp (From Howard Avenue to Huron Church Road) 7/19/2022 7/22/2022 Tuesday, July 19, 2022 to Friday, July 22, 2022

​E.C. Row Expressway Westbound ON ramp at Howard Avenue will be closed for approximately the next two days.

Brian Rempel (519) 255-6560 x4333 Coco Paving Complete road Complete All 07/19/2022 00:00:00 07/22/2022 00:00:00
E.C. Row Expressway Ramp and Lane Closures (From Lauzon Parkway to Jefferson Boulevard) 3/9/2021 3/9/2021 Tuesday, March 09, 2021 Ramp and Lane closures on E.C. Row Expressway between Jefferson Boulevard and Lauzon Parkway for guardrail repairs will affect traffic flow.

Closure of eastbound on-ramp at Lauzon Parkway, 9 a.m. to 12 p.m.
Closure of eastbound off-ramp at Lauzon Parkway and northbound lane restrictions, 12 p.m. to 2 p.m.
Westbound lane restrictions between Lauzon Parkway and Jefferson Boulevard, 12 p.m. to 3 p.m.
Michael Cappucci, Contracts Coordinator 519-255-6326 Royal Fence Complete None. Complete All 03/09/2021 00:00:00 03/09/2021 00:00:00
Ellrose Avenue and Milloy Street (From see description to see description) 7/21/2022 10/31/2022 Thursday, July 21, 2022 to Monday, October 31, 2022

​The Windsor Utilities Commission will be reconstructing the watermains on:

Ellrose Avenue from Milloy Street to Tecumseh Road East (Ward 5)

Milloy Street from Bernard Road to Aurthur Road (Ward 5)

WUC Contract 2022-009 Pre-Construction Letter Ellrose Milloy.pdfWUC Contract 2022-009 Pre-Construction Letter Ellrose Milloy.pdf

Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 D'Amore Construction Complete watermain Complete All 07/21/2022 00:00:00 10/31/2022 00:00:00
Ford Boulevard and South National Street (From Ford Boulevard to South National Street) 11/15/2021 12/17/2021 Monday, November 15, 2021 to Friday, December 17, 2021

​The Windsor Utilities Commission will be resconstructing the watermains on Ford Boulevard from South National Street to Reginald Street and on South National Street from Polonia Park Place to Ford Boulevard.

WUC Contract 2021-027 Pre-Construction Letter Ford.pdfWUC Contract 2021-027 Pre-Construction Letter Ford.pdf

Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 D'Amore Construction (2000) Ltd. Complete watermain Complete All 11/15/2021 00:00:00 12/17/2021 00:00:00
Francois Road (From Alice Street to Tecumseh Road East) 8/4/2022 11/11/2022 Thursday, August 04, 2022 to Friday, November 11, 2022

​The Windsor Utilities Commission will be resonstructing the watermains on:

Francois Road - Alice Street to Tecumseh Road East

WUC Contract 2022-009 Pre-Construction Letter Francois.pdfWUC Contract 2022-009 Pre-Construction Letter Francois.pdf


Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 D'Amore Construction Complete watermain Complete All 08/04/2022 00:00:00 11/11/2022 00:00:00
George Avenue (From Ontario Street to Tecumseh Road East) 4/4/2022 8/26/2022 Monday, April 04, 2022 to Friday, August 26, 2022

​The Windsor Utilities Commission will be reconstructing the watermains on: George Avenue from Ontario Street to Tecumseh Road East (Ward 5).

WUC Contract 2022-003 Pre-Construction Letter George.pdfWUC Contract 2022-003 Pre-Construction Letter George.pdf

Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 Major Construction (2010) Ltd. Complete watermain Complete All 04/04/2022 00:00:00 08/26/2022 00:00:00
Giles Boulevard East (From Parent Avenue to Gladstone Avenue) 7/4/2022 11/30/2022 Monday, July 04, 2022 to Wednesday, November 30, 2022

​Giles Boulevard East from Gladstone Avenue to Parent Avenue will be under construction for storm sewer, watermain and pavement rehabilitation work. Giles Boulevard East will be partially closed. The closure of lanes and intersections will depend on the progress of construction and may/may not permit local traffic and side road parking. Please follow the detour signage and drive carefully.

The intersection of Giles Boulevard East and Parent Avenue will be fully closed for constuction on Monday July 18, 2022 only. No traffic will be permitted. The purpose of this closure is to install new watermain as part of Giles Bolevard East Rehabilitation project.

Aojeen Issac, P. Eng. Engineering Department (519) 255-6257 x6368 J.C.S. Construction Inc. Current road,sewer,watermain Current All 07/04/2022 00:00:00 11/30/2022 00:00:00
Giles Boulevard East (From Ouellette Avenue to Dufferin Street) 9/15/2022 9/15/2022 Thursday, September 15, 2022

​Eastbound Giles Boulevard East will have lane restrictions between Ouellette Avenue and Dufferin Street for catch basin repairs. From 8:00am to 4:00pm on Thursday, September 15, 2022.

Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 DanRuss Complete catch basin Complete All 09/15/2022 00:00:00 09/15/2022 00:00:00
Gladstone Avenue and Seneca Street (From see description to see description) 6/6/2022 8/26/2022 Monday, June 06, 2022 to Friday, August 26, 2022

​The Windsor Utlilties Commission will be reconstructing the watermains on:

Gladstone Avenue from Tecumseh Road East to Seneca Street (Ward 4)

Seneca Street from Gladstone Avenue to Moy Avenue (Ward 4)

City Ops Contract 18-22 Pre-Construction Letter Gladstone Seneca.pdfCity Ops Contract 18-22 Pre-Construction Letter Gladstone Seneca.pdf

Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 D'Amore Construction Complete watermain Complete All 06/06/2022 00:00:00 08/26/2022 00:00:00
Gladstone Avenue and Vimy Avenue (From see description to see description) 10/31/2022 11/1/2022 Monday, October 31, 2022 to Tuesday, November 01, 2022

​Gladstone Avenue will be closed for road repairs from Tecumseh Road East to Ypres Avenue and Vimy Avenue will be closed from Gladstone Avenue to Lincoln Road.

Daryl Lundy, A.Sc.T., Contracts Supervisor (519) 255-6560 x4330 Coco Paving Complete road Complete All 10/31/2022 00:00:00 11/01/2022 00:00:00
Gladstone Avenue and Ypres Avenue (From Gladstone Avenue to Ypres Avenue) 6/9/2021 11/30/2021 Wednesday, June 09, 2021 to Tuesday, November 30, 2021

​Gladstone Avenue from Tecumseh Road East to Ypres Avenue as well as Ypres Avenue from Forest Avenue to Walker Road will be under road and  watermain construction for approximately 5 months. Gladstone Avenue will be closed and Ypres Avenue will be partially closed (westbound) for the duration of construction to local traffic only. Travellers should expect long delays and avoid area if possible. To complete the project as fast as possible, construction will occur simultaneously between the two streets (when possible).

Michael Cappucci, P. Eng. Contracts Coordinator (519) 255-61000 x4234 Sterling Ridge Group Inc. Complete road,watermain Complete All 06/09/2021 00:00:00 11/30/2021 00:00:00
Glenwood Pedestrian Bridge Closure (Grand Marais Drain) 7/25/2022 9/30/2022 Monday, July 25, 2022 to Friday, September 30, 2022

​Glenwood Pedestrian Bridge over Grand Marais Drain will be closed for reconstruction. No pedestrian access will be allowed during construction. From Monday, July 25 until Friday, September 30, 2022.

Phong Nguy Manager of Contracts, Field Services and Maintenance (519) 255-6326 Front Construction Industries Inc. Complete bridge Complete All 07/25/2022 00:00:00 09/30/2022 00:00:00
Glidden Avenue (From Wyandotte Street East to CNR rail tracks) 3/2/2022 6/10/2022 Wednesday, March 02, 2022 to Friday, June 10, 2022

​The Windsor Utilities Commission will be reconstructing the watermains on Glidden Avenue from Wyandotte Street East to CNR Tracks (Ward 6).

WUC Contract 2021-027 Pre-Construction Letter Glidden.pdfWUC Contract 2021-027 Pre-Construction Letter Glidden.pdf

Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 D'Amore Construction (2000) Ltd. Complete watermain Complete All 03/02/2022 00:00:00 06/10/2022 00:00:00
Hawthorne Drive (From Roseville Park to Lauzon Road) 5/11/2022 7/25/2022 Wednesday, May 11, 2022 to Monday, July 25, 2022

​Partial lane closures along Hawthorne Drive for the construction of asphalt pathways. Work will primarily take place off the roadway, but lane restrictions may occasionally be required. A flag person will be present when traffic is reduced to one lane of traffic.

Juan Paramo, Transportation Planning (519) 999-6378 PieraCon Complete road Complete All 05/11/2022 00:00:00 07/25/2022 00:00:00
Howard Avenue and Tecumseh Road East Intersection (From Howard Avenue to Tecumseh Road East) 10/23/2022 10/27/2022 Sunday, October 23, 2022 to Thursday, October 27, 2022

​The intersection of Howard Avenue and Tecumseh Road East will have lane restrictions for road work during the overnight hours. From 10:00pm to 5:00am on Sunday, October 23, until Thursday, October 27, 2022.

Tony Varacalli Maintenance Supervisor (519) 255-6560 x4268 Villa Construction Complete road Complete All 10/23/2022 00:00:00 10/27/2022 00:00:00
Huron Church Road (From College Avenue to Wyandotte Street West) 6/24/2022 6/26/2022 Friday, June 24, 2022 to Sunday, June 26, 2022

​Northbound Huron Church Road between College Avenue and Wyandotte Street West will have lane restrictions for spray patching. From 6:00am to 6:00pm on Friday, June 24 and Sunday, June 26, 2022.

Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 Alite Spray Patching Complete road Complete All 06/24/2022 00:00:00 06/26/2022 00:00:00
Huron Church Road (From Dorchester Road to Tecumseh Road West) 8/22/2022 11/25/2022 Monday, August 22, 2022 to Friday, November 25, 2022

​Huron Church Road will have continued lane restrictions between Dorchester Road and Tecumseh Road West for road repairs. However, northbound traffic will be increased to two lanes from the current single lane. Please slow down and use caution in constrcution zone. Ongoing from 7:00am to 7:00pm until Friday, November 25, 2022.

Charles Hartford Contracts Coordinator Operations (519) 255-6326 x4234 PieraCon Complete road Complete All 08/22/2022 00:00:00 11/25/2022 00:00:00
Iroquois Street (From Windermere Road to Argyle Road) 3/14/2022 5/20/2022 Monday, March 14, 2022 to Friday, May 20, 2022

​As part of an ongoiong infrastructure renewal program, the Windsor Utilities Commission (WUC) will be installing a new 200mm PVC watermain on Iroquois Street from Windermere Road to Argyle Road (Ward 4). The project should take approximately 10 weeks to complete. Project timing is weather dependent. Tree trimming will also occur in advance by a certified sub-contractor.

WUC Contract 2021-048 Pre-Construction Letter Iroquois.pdfWUC Contract 2021-048 Pre-Construction Letter Iroquois.pdf

Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 D'Amore Construction (2000) Ltd. Complete watermain Complete All 03/14/2022 00:00:00 05/20/2022 00:00:00
Jefferson Boulevard (From South National Street to Edgar Street) 11/15/2022 11/15/2022 Tuesday, November 15, 2022

​Jefferson Boulevard wil be closed at the VIA Rail tracks between South National Street and Edgar Street for road repairs. From 7:00am to 6:00pm on Tuesday, November 15, 2022.

Daryl Lundy, A.Sc.T., Contracts Supervisor (519) 255-6560 x4330 Mill Am Complete road Complete All 11/15/2022 00:00:00 11/15/2022 00:00:00
Jos St Louis (From Rose Street to Tecumseh Road East) 8/8/2022 11/4/2022 Monday, August 08, 2022 to Friday, November 04, 2022

​Jos St Louis Avenue from Rose Street to Tecumseh Road East will be closed for approximately 3 months for storm sewer, sanitary sewer , pavement and water services rehabilitation. Local traffic will be permitted only. The southbound traffic on Jos St Louis Avenue will be shifted around the area of construction. There will be temporary lane closures on Tecumseh Road East from Rivard Avenue to Clemenceau Boulevard for approximately one week for sewer work in the Jos St Louis Avenue and Tecumseh Road East intersection.

Curb work at the Jos St. Louis/Tecumseh Road East intersection will result in temporary lane closure on Tecumseh Road East and Rivard Avenue to Clemenceau Boulevard for approximately two days. From Friday, October 28, 2022 until Saturday, October 29, 2022.

Patrick Muzyka, P. Eng. Technologist III (519) 255-6100 x6472 D'Amore Construction (2000) Ltd. Complete sewer,road,watermain Complete All 08/08/2022 00:00:00 11/04/2022 00:00:00
Kildare Road (From Tecumseh Road East to Seneca Street) 8/8/2022 10/28/2022 Monday, August 08, 2022 to Friday, October 28, 2022

​The Windsor Utilities Commission will be reconstructing the watermains on:

Kildare Road - Tecumseh Road East to Seneca Street

City Ops Contract 18-22 Pre-Construction Letter Kildare.pdfCity Ops Contract 18-22 Pre-Construction Letter Kildare.pdf

Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 D'Amore Construction Complete watermain Complete All 08/08/2022 00:00:00 10/28/2022 00:00:00
Langlois Avenue (From Giles Boulevard East to Shepherd Street East) 5/18/2022 7/15/2022 Wednesday, May 18, 2022 to Friday, July 15, 2022

​Langlois Avenue is closed between Giles Boulevard East and Shepherd Street East for road and watermain reconstruction. Access for local traffic only. Ongoing until Friday, July 15, 2022.

Daniel Lopez - Engineer I Public Works Operations (519) 945-9971 D'Amore Construction (2000) Ltd. Complete road,watermain Complete All 05/18/2022 00:00:00 07/15/2022 00:00:00
Lauzon Parkway (From Twin Oaks Drive to CP Rail Bridge) 8/22/2022 10/1/2022 Monday, August 22, 2022 to Saturday, October 01, 2022

​Lauzon Parkway will have lane restrictions over the CP Rail bridge just south of Twin Oaks Drive for bridge repairs and paving. Please slow down and use caution in the construction zone.

Charles Hartford Contracts Coordinator Operations (519) 255-6326 x4234 Front Construction Industries Inc. Complete bridge,road Complete All 08/22/2022 00:00:00 10/01/2022 00:00:00
Lauzon Parkway (From Forest Glade Drive to E.C. Row Expressway) 10/13/2022 10/13/2022 Thursday, October 13, 2022

​Northbound Lauzon Parkway will have lane restrictions between Forest Glade Drive and the E.C. Row Expressway for manhole repairs. From 8:00am to 6:00pm, Thursday, October 13, 2022.

Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 DanRuss Complete sewer Complete All 10/13/2022 00:00:00 10/13/2022 00:00:00
Lincoln Road (From Tecumseh Road East to Seneca Street) 5/24/2022 7/29/2022 Tuesday, May 24, 2022 to Friday, July 29, 2022

​Lincoln Road will be closed between Tecumseh Road East and Seneca Street for road and watermain work. Local traffic only. From Tuesday, May 24 to Friday, July 29, 2022.

Daryl Lundy, A.Sc.T., Contracts Supervisor (519) 255-6560 x4330 D'Amore Construction (2000) Ltd. Complete road,watermain Complete All 05/24/2022 00:00:00 07/29/2022 00:00:00
Louis Avenue (From Erie Street East to Giles Boulevard East) 2/22/2022 4/22/2022 Tuesday, February 22, 2022 to Friday, April 22, 2022

​The Windsor Utilities Commission will be reconstructing the watermains on Louis Avenue from Erie Street East to Giles Boulevard East (Ward 4).

WUC Contract 2021-048 Pre-Construction Letter Louis.pdfWUC Contract 2021-048 Pre-Construction Letter Louis.pdf

Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 D'Amore Construction (2000) Ltd. Complete watermain Complete All 02/22/2022 00:00:00 04/22/2022 00:00:00
Lynngrove Crescent, Lynngrove Court and Melville Drive (From see description to see description) 9/23/2022 11/18/2022 Friday, September 23, 2022 to Friday, November 18, 2022

​Lynngrove Crescent, Lynngrove Court and Melville Drive will be closed for approximately seven weeks for curb repairs as well as milling and paving work. Local traffic only. From Friday, September 23 until Friday, November 18, 2022.

Daryl Lundy, A.Sc.T., Contracts Supervisor (519) 255-6560 x4330 Amico Infrastructures Inc. Complete curb,road Complete All 09/23/2022 00:00:00 11/18/2022 00:00:00
Mark Avenue (From Campbell Avenue to Algonquin Street) 9/13/2021 12/22/2021 Monday, September 13, 2021 to Wednesday, December 22, 2021

​Mark Avenue from Campbell Avenue to Algonquin Street will be closed for approximately 4 months for sewer, pavement and watermain rehabilitation. Local traffic will be permitted only. The southbound lane of Campbell at Mark Avenue will be closed as needed.

Joe Bressan, Engineering 1,Operations (519) 255-6100 x6890 D'Amore Construction (2000) Inc. Complete road,sewer,watermain Complete All 09/13/2021 00:00:00 12/22/2021 00:00:00
Matchette Road (From Broadway Street to E.C. Row Expressway) 9/14/2022 11/4/2022 Wednesday, September 14, 2022 to Friday, November 04, 2022

​Matchette Road will have lane narrowing between Broadway Street and the westbound E.C. Row Expressway off-ramp for construction of a multi-use trail. Please watch for pylons and use caution where workers are present.

Josie Liburdi Project Coordinator Engineering (519) 255-6100 x6145 Sterling Ridge Infrastructure Inc. Complete road Complete All 09/14/2022 00:00:00 11/04/2022 00:00:00
Matthew Brady (From St. Rose Avenue to Wyandotte Street East) 8/29/2022 11/30/2022 Monday, August 29, 2022 to Wednesday, November 30, 2022

​Matthew Brady Boulevard from St. Rose Avenue to Wyandotte Street East will be closed for approximately 3 months for storm sewer, sanitary sewer, watermain and pavement rehabilitation. There will be a temporary lane closure of the eastbound lanes on Wyandotte Street East from Eastlawn Avenue to St. Paul Avenue for approximately four weeks, Monday, September 5, 2022 to Friday, September 30, 2022 for sewer work in the Matthew Brady Boulevard and Wyandotte Street Intersection. During this time Wyandotte Street East will be reduced to two lanes, one in each direction.

Adam Mourad, P. Eng. (519) 255-6100 x6614 Old Castle Contracting Inc. Current road,sewer,watermain Current All 08/29/2022 00:00:00 11/30/2022 00:00:00
McDougall and Chatham Street Intersection (From Glengarry Street to Charles Clark Square) 11/7/2022 11/28/2022 Monday, November 07, 2022 to Monday, November 28, 2022

​The intersection of McDougall Street and Chatham Street East will be closed for road repairs and Chatham Street East will have lane restrictions from Glengarry Street to Charles Clark Square. On Monday, November 7 until Monday, November 28, 2022.

Anthony Ferro, Contracts Supervisor Operations (519) 255-2560 x4252 Giorgi Construction Complete road Complete All 11/07/2022 00:00:00 11/28/2022 00:00:00
McDougall Street (From Holden Avenue to Eugenie Street East) 8/30/2022 9/14/2022 Tuesday, August 30, 2022 to Wednesday, September 14, 2022

​Southbound McDougall Street will have lane restrictions between Holden Avenue and Eugenie Street East for sidewalk reconstruction. Flag persons will be present. From 7:00am to 7:00pm on Tuesday, August 30 until Wednesday, September 14, 2022.

Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 PieraCon Complete sidewalk Complete All 08/30/2022 00:00:00 09/14/2022 00:00:00
North Talbot Road (From Howard Avenue to Southwood Lakes Boulevard) 4/11/2022 6/17/2022 Monday, April 11, 2022 to Friday, June 17, 2022

​Installation of storm sewers, road widening (including bike lanes and sidewalks) and streetlights on North Talbot Road from Howard Avenue to east of Southwood Lakes Boulevard. Local Traffic only.

Paul Mourad, P. Eng. (519) 562-2448 SheaRock Construction Group Inc. Complete sidewalk,road,sewer Complete All 04/11/2022 00:00:00 06/17/2022 00:00:00
Ojibway Parkway (From see description to see description) 10/19/2022 10/21/2022 Wednesday, October 19, 2022 to Friday, October 21, 2022

​North and southbound Ojibway Parkway will have lane closures in both directions between Weaver Road and Broadway Street for mill and pave work from 7:00am to 7:00pm on Wednesday, October 19, and Thursday, October 20, 2002 (weather permitting).

The intersection of Ojibway Parkway and Sprucewood Avenue will also have lane restrictions for mill and pave repair from 7:00am to 7:00pm on Friday, October 21 (weather permitting). Also during Friday's construction, north and southbound left-turn lanes on Ojibway Parkway will be closed and Eastbound through traffic on Sprucewood Avenue will be restricted and detoured to Weaver Road.

Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 Mill Am Complete road Complete All 10/19/2022 00:00:00 10/21/2022 00:00:00
Olive Road and Empress Street (From see description to see description) 10/13/2022 10/21/2022 Thursday, October 13, 2022 to Friday, October 21, 2022

​Olive Road will be closed between Milloy Street and Tecumseh Road East, and Empress Street will be closed between Norman Road and Pillette Road for placement of surface asphalt. Local traffic only. From Thursday, October 13 to Friday, October 21, 2022.

Daryl Lundy, A.Sc.T., Contracts Supervisor (519) 255-6560 x4330 Coco Paving Complete road Complete All 10/13/2022 00:00:00 10/21/2022 00:00:00
Ouellette Avenue (From Erie Street to Elliott Street) 8/15/2022 8/16/2022 Monday, August 15, 2022 to Tuesday, August 16, 2022

​Northbound Ouellette Avenue will have lane restrictions between Erie Street and Elliott Street for catch basin repairs. From 7:00am to 5:00pm on Monday, August 15 and Tuesday, August 16, 2022.

Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 DanRuss Complete catch basin Complete All 08/15/2022 00:00:00 08/16/2022 00:00:00
Ouellette Avenue (From Riverside Drive to Pitt Street) 10/13/2022 10/21/2022 Thursday, October 13, 2022 to Friday, October 21, 2022

​Northbound Ouellette Avenue will have lane restrictions between Riverside Drive and Pitt Street for sidewalk work. From 6:30am to 6:00pm on Thursday, October 13 until Friday, October 21, 2022.

Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 Villa Construction Complete sidewalk Complete All 10/13/2022 00:00:00 10/21/2022 00:00:00
Parkside Court (From Beals Street West to 1548 Parkside Court) 11/16/2020 12/7/2020 Monday, November 16, 2020 to Monday, December 07, 2020

​Parkside Court will be closed from Beals Street West to 1548 Parkside Court for Watermain Reconstruction.

Spencer Johnston, WUC 519-251-7300 x 609 To be determined. Complete watermain Complete All 11/16/2020 00:00:00 12/07/2020 00:00:00
Provincial Road and Sixth Concession Road (From see description to see description) 9/12/2022 11/30/2022 Monday, September 12, 2022 to Wednesday, November 30, 2022

​Alternating lane restrictions will be in place on Provincial Road from south of Cabana Road East to Walker Road as well as Sixth Concession Road from Cabana Road East to the CN Rail Tracks for watermain and utility work.

Sixth Concession Road - Cabana Road East to North of CN Rail road closure

As part of the Provincial Division Corridor Improvements, Phase 3, Sixth Concession Road from Cabana Road East to Provincial Road will be closed. Flag persons will be located at each intersection to direct traffic wishing to access businesses. All parties to follow posted detour route. From Monday October 31, 2022 to Friday November 25, 2022.

Paul Mourad, P. Eng. (519) 255-6100 x6119 Green Infrastructure Partners Inc. Current watermain Current All 09/12/2022 00:00:00 11/30/2022 00:00:00
Randolph Avenue (From Cleary Street to Northwood Street) 9/13/2021 12/17/2021 Monday, September 13, 2021 to Friday, December 17, 2021

​Randolph Avenue from Cleary Street to Northwood Street will be closed for storm sewer, pavement, watermain streetlighting rehabilitation and local improvement work. Local traffic only.

Sarah Meneses, P. Eng. (519) 255-6100 x6336 J.C.S. Construction Inc. Complete road,sewer,watermain Complete All 09/13/2021 00:00:00 12/17/2021 00:00:00
Rankin Avenue (From Wyandotte Street West to Union Street) 11/2/2022 11/7/2022 Wednesday, November 02, 2022 to Monday, November 07, 2022

​Rankin Avenue will be closed between Wyandotte Street West and Union Street for surface asphalt work. No parking on the street from 7:00am to 7:00pm. On Wednesday, November 2 until Monday, November 7, 2022.

Daryl Lundy, A.Sc.T., Contracts Supervisor (519) 255-6560 x4330 Coco Paving Complete road Complete All 11/02/2022 00:00:00 11/07/2022 00:00:00
Riberdy Road (From EC Row to Foster Ave) 7/4/2022 9/23/2022 Monday, July 04, 2022 to Friday, September 23, 2022

The Windsor Utilities Commission will be reconstructing the watermains on:

Riberdy Road from EC Row to Foster Ave.

WUC Contract 2022-014 Pre-Construction Letter Riberdy.pdfWUC Contract 2022-014 Pre-Construction Letter Riberdy.pdf



Spencer Johnston, Manager Water Construction & Design (519)251-7300 x609 SheaRock Construction Complete watermain Complete All 07/04/2022 00:00:00 09/23/2022 00:00:00
Rivard Avenue (From Adstoll Avenue to Rose Avenue) 10/17/2022 10/21/2022 Monday, October 17, 2022 to Friday, October 21, 2022

​Rivard Avenue will have lane restrictions between Adstoll Avenue and Rose Avenue for milling and paving work. Flag persons will be on-site. From Monday, October 17 until Friday, October 21, 2022.

Daryl Lundy, A.Sc.T., Contracts Supervisor (519) 255-6560 x4330 Coco Paving Complete road Complete All 10/17/2022 00:00:00 10/21/2022 00:00:00
Riverdale Avenue (From Wyandotte Street East to Menard Street) 9/19/2022 9/23/2022 Monday, September 19, 2022 to Friday, September 23, 2022

​Riverdale Avenue will be down to one lane between Wyandotte Street East and Menard Street for milling and paving work. Flag persons will be on site. From Monday, September 19 to Friday, September 23, 2022 (weather permitting).

Daryl Lundy, A.Sc.T., Contracts Supervisor (519) 255-6560 x4330 Coco Paving Complete road Complete All 09/19/2022 00:00:00 09/23/2022 00:00:00
Riverside Drive East (From Rossini Boulevard to Jos Janisse Avenue) 10/31/2022 10/31/2022 Monday, October 31, 2022

​Westbound Riverside Drive East will have lane restrictions between Rossini Boulevard and Jos Janisse Avenue for catch basin repairs. Flag persons will be on site. From 8:00am to 6:00pm on Monday, October 31, 2022.

Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 DanRuss Complete catch basin Complete All 10/31/2022 00:00:00 10/31/2022 00:00:00
Riverside Drive East (From Ouellette Avenue to Goyeau Street) 11/11/2022 11/28/2022 Friday, November 11, 2022 to Monday, November 28, 2022

​Westbound Riverside Drive East will have lane restrictions between Ouellette Avenue and Goyeau Street for road and sidewalk repairs. On Friday, November 11 until Monday, November 28, 2022.

Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 PieraCon Complete road,sidewalk Complete All 11/11/2022 00:00:00 11/28/2022 00:00:00
Riverside Drive West (From Caron Avenue to Church Street) 8/2/2022 8/19/2022 Tuesday, August 02, 2022 to Friday, August 19, 2022

​Westbound Riverside Drive West will have lane restrictions between Caron Avenue and Church Street for sidewalk construction.

Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 PieraCon Complete sidewalk,road Complete All 08/02/2022 00:00:00 08/19/2022 00:00:00
Riverside Drive West (From Huron Church Road to Sandwich Roundabout) 8/13/2022 9/30/2022 Saturday, August 13, 2022 to Friday, September 30, 2022

​Riverside Drive will be closed between Huron Church / Sandwich Roundabout for overhead bridge work. Local access from Sandwich Roundabout only.

Susan Clark 519-977-0700 x 3086 To be determined. Complete bridge Complete All 08/13/2022 00:00:00 09/30/2022 00:00:00
Rooney Street/Josephine Avenue (From see description to see description) 5/10/2022 8/16/2022 Tuesday, May 10, 2022 to Tuesday, August 16, 2022

​Rooney Street will be closed from Campbell Avenue to Partington Avenue and Josephine Avenue will be closed from Rooney Street to Wyandotte Street West for road and watermain reconstruction. Local traffic only.

Daniel Lopez - Engineer I Public Works Operations (519) 945-9971 J.C.S. Construction Inc. Complete road,watermain Complete All 05/10/2022 00:00:00 08/16/2022 00:00:00
Roseville Garden Drive (From Tecumseh Road East to Jefferson Boulevard) 10/4/2022 10/18/2022 Tuesday, October 04, 2022 to Tuesday, October 18, 2022

​Roseville Garden Drive will have intermitten lane restrictions between Tecumseh Road East and Jefferson Boulevard for sidewalk work. Flag persons will be on-site. From Tuesday, October 4 until, Tuesday, October 18, 2022.

Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 PieraCon Complete sidewalk Complete All 10/04/2022 00:00:00 10/18/2022 00:00:00
Sandwich Street (From Ojibway Parkway to Chappell Avenue) 11/7/2022 12/30/2022 Monday, November 07, 2022 to Friday, December 30, 2022

​The Windsor Utilities Commission will be reconstructing the watermains on Sandwich Street from Ojibway Parkway to Chappell Avenue (Ward 1 and 2)

WUC Contract 2022-015 Pre-Construction Letter Sandwich.pdfWUC Contract 2022-015 Pre-Construction Letter Sandwich.pdf

Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 SheaRock Construction Group Inc. Current watermain Current All 11/07/2022 00:00:00 12/30/2022 00:00:00
Seminole Street (From Walker Road to St. Luke Road) 8/25/2022 9/7/2022 Thursday, August 25, 2022 to Wednesday, September 07, 2022

​Westbound Seminole Street between Walker Road and St. Luke Road will have lane restrictions for sidewalk reconstruction. From August 25 to September 7, 2022, 7:00am to 7:00pm daily.

Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 PieraCon Complete sidewalk Complete All 08/25/2022 00:00:00 09/07/2022 00:00:00
Seventh Concession (From Baseline Road to Walker Road) 11/21/2022 11/22/2022 Monday, November 21, 2022 to Tuesday, November 22, 2022

​Seventh Concession will be closed at the CN Rail tracks between Baseline Road and Walker Road for mill and pave work. No through traffic will be allowed. From 7:00am Monday, November 21, to 12:00 noon Tuesday, November 22, 2022.

Daryl Lundy, A.Sc.T., Contracts Supervisor (519) 255-6560 x4330 Coco Paving Complete road Complete All 11/21/2022 00:00:00 11/22/2022 00:00:00
Tecumseh Road East (From Forest Glade Drive to Clover Avenue) 3/10/2021 8:00 AM 3/11/2021 5:00 PM Wednesday, March 10, 2021 8:00 AM to Thursday, March 11, 2021 5:00 PM

​Tecumseh Road East currently has eastbound lane restrictions between Forest Glade and Clover Avenue for catch basin repairs.

Roberta Harrison, Maintinance Corrdinator, (519) 266-65660 x4241 DanRuss Complete sewer Complete All 03/10/2021 08:00:00 03/11/2021 17:00:00
Tecumseh Road East (From Rivard Avenue to Clemenceau Boulevard) 8/15/2022 8/19/2022 Monday, August 15, 2022 to Friday, August 19, 2022

​Tecumseh Road East will be reduced to one lane between Rivard Avenue and Clemenceau Boulevard for sewer work. Flag persons will be present to direct the flow of traffic. Outside of work hours, traffic will be open to one lane in each direction. From 7:00am to 7:00pm on Monday, August 15 to Friday, August 19, 2022.

Patrick Muzyka, P. Eng. Technologist III (519) 255-6100 x6472 D'Amore Construction (2000) Ltd. Complete road,sewer Complete All 08/15/2022 00:00:00 08/19/2022 00:00:00
Tourangeau Road (From Milloy Street to Tecumseh Road East) 5/16/2022 8/5/2022 Monday, May 16, 2022 to Friday, August 05, 2022

​The Windsor Utilities Commission will be reconstructing the watermains on:

Tourangeau Road from Milloy Street to Tecumseh Road East (Ward 5).

WUC Contract 2022-003 Pre-Construction Letter Tourangeau.pdfWUC Contract 2022-003 Pre-Construction Letter Tourangeau.pdf

Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 Major Construction (2010) Ltd. Complete watermain Complete All 05/16/2022 00:00:00 08/05/2022 00:00:00
Turner Road, Byng Road, EC Row Avenue (From see description to see description) 5/23/2022 8/12/2022 Monday, May 23, 2022 to Friday, August 12, 2022

​The Windsor Utilities Commission will be reconstructing the watermains on:

Turner Road - EC Row Avenue to Sydney Avenue (Ward 9)

Byng Road - EC Row Avenue to Sydney Avenue (Ward 9)

EC Row Avenue - Byng Road to Walker Road (Ward 9)

WUC Contract 2022-014 Pre-Construction Letter TBE.pdfWUC Contract 2022-014 Pre-Construction Letter TBE.pdf

Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 Sherway Construction Complete watermain Complete All 05/23/2022 00:00:00 08/12/2022 00:00:00
Walker Road (From Riverside Drive East to Wyandotte Street East) 7/13/2022 8/2/2022 Wednesday, July 13, 2022 to Tuesday, August 02, 2022

​Walker Road between Riverside Drive East and Wyandotte Street East will be closed for railroad and road work.

CJ Hartford Contracts Coordinator Operations (519) 255-6560 x4234 D'Amore Construction Complete railroad,road Complete All 07/13/2022 00:00:00 08/02/2022 00:00:00
Walker Road (From Cataraqui Street to Wyandotte Street East) 8/17/2022 8/17/2022 Wednesday, August 17, 2022

​Southbound Walker Road will have lane restrictions between Cataraqui Street and Wyandotte Street East for manhole repair. From 7:00am to 7:00pm on Wednesday, August 17, 2022.

Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 DanRuss Complete sewer Complete All 08/17/2022 00:00:00 08/17/2022 00:00:00
Walker Road (From Grand Marais Road East to Parkdale Place) 10/11/2022 10/15/2022 Tuesday, October 11, 2022 to Saturday, October 15, 2022

​Walker Road will be reduced to one lane in each direction between Grand Marais Road East and Parkdale Place for drain culvert repairs. Business access will be maintained, however, no left turns will be permitted in the work zone. From Tuesday, October 11, until Saturday, October 15, 2022.

Charles Hartford Contracts Coordinator Operations (519) 255-6326 x4234 Front Construction Industries Inc. Complete None. Complete All 10/11/2022 00:00:00 10/15/2022 00:00:00
Walker Road (From Ottawa Street to Seminole Street) 10/20/2022 10/21/2022 Thursday, October 20, 2022 to Friday, October 21, 2022

​Walker Road will be closed at the railway tracks between Ottawa Street and Seminole Street for track repairs. Detour signage will be in place. From 5:00am Thursday, Ocotber 20 until 6:00pm Friday, October 21, 2022.

ETR Daryl Potter (519) 567-0684 or Mike Spagnuolo (519) 255-6727 Diponti Paving Complete railroad Complete All 10/20/2022 00:00:00 10/21/2022 00:00:00
Wellington Avenue (From College Avenue to Elliott Street West) 10/19/2022 10/19/2022 Wednesday, October 19, 2022

​Wellington Avenue will be closed between College Avenue and Elliott Street West for railway track repairs. Detour signage will be in place. From 6:30am to 6:00pm on Wednesday, October 19, 2022.

Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 Diponti Paving Complete railroad Complete All 10/19/2022 00:00:00 10/19/2022 00:00:00
Westminster Boulevard (From Wyandotte Street East to CNR rail tracks) 10/18/2021 12/10/2021 Monday, October 18, 2021 to Friday, December 10, 2021

​As part of an ongoing infrastructure renewal program, the Windsor Utilities Commission (WUC) will be installing a new 200mm PVC watermain on Westminster Boulevard from Wyandotte Street East to CNR rail tracks by horizontal directional drilling method. Work is scheduled to begin the week of October 18, 2021. The project should take approximately 8 weeks to complete. Project timing is weather dependant. Tree trimming will also occur in advance by a certified sub-contractor.

Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 D'Amore Construction (2000) Ltd. Complete watermain Complete All 10/18/2021 00:00:00 12/10/2021 00:00:00
Westminster Boulevard (From Tecumseh Road East to Adstoll Avenue) 4/5/2022 6/30/2022 Tuesday, April 05, 2022 to Thursday, June 30, 2022

​Westminster Boulevard, Tecumseh Road East to Adstoll Avenue will be closed for approximately 3 months for road and watermain reconstruction. Local traffic will be permitted only.

Daryl Lundy, A.Sc.T., Contracts Supervisor (519) 255-6560 x4330 JCS Complete road,watermain Complete All 04/05/2022 00:00:00 06/30/2022 00:00:00
Wyandotte Street East (From Wyandotte Street East to Eastlawn Avenue) 6/7/2022 6/14/2022 Tuesday, June 07, 2022 to Tuesday, June 14, 2022

Lanes closure of Wyandotte Street East at Eastlawn intersection will be in two phases.

Phase 1 will include the closure of the outside lanes of Wyandotte Street East at the intersection of Eastlawn Avenue for a week, while the inside lanes will be open for traffic.

Phase 2 will follow the completion of Phase 1, where the inside lanes of Wyandotte Street East will be closed for construction, while the outside lanes will be open to traffic.

The purpose of this closure is to restore the concrete pavement at this intersection as part of Eastlawn Avenue Reconstruction project.

Please follow the detour signage and drive carefully.

Phase 1: Tuesday, June 7 at 7:00am to Tuesday, June 14 at 7:00pm.

Phase 2: TBD

Aojeen Issac, Engineer II (519) 255-6257 x6368 Sterling Ridge Group Inc. Complete road Complete All 06/07/2022 00:00:00 06/14/2022 00:00:00
Wyandotte Street East (From Lauzon Road to St. Rose Avenue) 8/25/2022 9/7/2022 Thursday, August 25, 2022 to Wednesday, September 07, 2022

​Eastbound Wyandotte Street East will have lane restrictions between Lauzon Road and St. Rose Avenue for road repairs.

Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 Villa Construction Complete road Complete All 08/25/2022 00:00:00 09/07/2022 00:00:00
Wyandotte Street East (From Eastlawn Avenue to St. Paul Avenue) 9/5/2022 9/30/2022 Monday, September 05, 2022 to Friday, September 30, 2022

​Wyandotte Street East will be reduced to two lanes between Eastlawn Avenue and St. Paul Avenue for sewer work. From Monday, September 5 until Friday, September 30, 2022.

Adam Mourad, P. Eng. (519) 255-6100 x6614 Old Castle Contracting Inc. Complete sewer Complete All 09/05/2022 00:00:00 09/30/2022 00:00:00
Wyandotte Street East (From Homedale Boulevard to St. Mary's Boulevard) 10/4/2022 10/6/2022 Tuesday, October 04, 2022 to Thursday, October 06, 2022

​Eastbound Wyandotte Street East has lane restrictions between Homedale Boulevard and St. Mary's Boulevard for sewer repairs. Ongoing until Thursday, October 6 2022 from 9:00am to 6:00pm.

Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 DanRuss Complete sewer Complete All 10/04/2022 00:00:00 10/06/2022 00:00:00
Wyandotte Street East (From Belleperche Place to Isabelle Place) 11/10/2022 11/11/2022 Thursday, November 10, 2022 to Friday, November 11, 2022

​Wyandotte Street East will have lane restrictions between Belleperche Place and Isabelle Place for catch basin repairs. From 8:00am to 3:00pm on Thursday, November 10 and Friday, November 11, 2022.

Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 DanRuss Complete catch basin Complete All 11/10/2022 00:00:00 11/11/2022 00:00:00

Projects Under Construction

For information on projects currently under construction, click here to launch the Construction and Detours mapping application

Projects Scheduled for Construction

For information on sewers, road widening, street lighting, City-owned facilities, and new subdivisions scheduled for construction in the near future, use the database above. For descriptions of some maintenance activities, please consult the following pages:

Building Windsor's Future

The City of Windsor will undergo a physical transformation over the coming years due to a significant investment in capital projects. For a detailed list of current projects please visit the Building Windsor's Future page. 

Engineering Requirements for Development in the Public Right-of-Way

For information on the City's engineering standards for construction works within the public right of way, please consult the Public Infrastructure & Right-of-Way Requirements page.

Engineering Department
350 City Hall Square West, 3rd Floor
P. O. Box 1607
Windsor, Ontario
Canada
N9A 6S1

Phone: For general information, call 311. For detailed inquires, call 519-255-6257.
Fax: 519-255-9847
Email: engineeringdept@citywindsor.ca

​​​​ ​​​​​​​