Argyle Road, Richmond Street and Devonshire Road (From see description to see description) |
4/4/2022 |
7/22/2022 |
Monday, April 04, 2022 to Friday, July 22, 2022 |
The Windsor Utilities Commission will be reconstructing the watermains on:
Argyle Road - Richmond Street to Ottawa Street (Ward 4)
Richmond Street - Argyle Road to Devonshire Road (Ward 4)
Devonshire Road - Richmond Street to Willistead Crescent (Ward 4)
WUC Contract 2022-002 Pre-Construction Letter DAR.pdf
|
Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 |
D'Amore Construction (2000) Ltd. |
Complete |
watermain |
Complete All |
04/04/2022 00:00:00 |
07/22/2022 00:00:00 |
Argyle Road/Niagara Street (From see description to see description) |
5/16/2022 |
8/19/2022 |
Monday, May 16, 2022 to Friday, August 19, 2022 |
The Windsor Utilities Commission will be reconstructing the watermains on:
Argyle Road from Wyandotte Street East to Niagara Street (Ward 4)
Niagara Street from Kildare Road to Walker Road (Ward 4)
WUC Contract 2022-002 Pre-Construction Letter Argyle Niagara.pdf
|
Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 |
D'Amore Construction (2000) Ltd. |
Complete |
watermain,bridge |
Complete All |
05/16/2022 00:00:00 |
08/19/2022 00:00:00 |
Arthur Road (From Ontario Street to VIA Rail) |
8/31/2022 |
11/30/2022 |
Wednesday, August 31, 2022 to Wednesday, November 30, 2022 |
Arthur Road will be closed for storm and sanitary sewer, watermain and pavement rehabilitation from Ontario Street to VIA Rail. Local Traffic Only.
|
Sarah Meneses, P. Eng. (519) 255-6100 x6336 |
SheaRock Construction Group Inc. |
Complete |
road,sewer,watermain |
Complete All |
08/31/2022 00:00:00 |
11/30/2022 00:00:00 |
Aubin Road and Reginald Street (From see description to see description) |
7/18/2022 |
12/23/2022 |
Monday, July 18, 2022 to Friday, December 23, 2022 |
Aubin Road from Seminole Street to Alice Street and Reginald Street from Aubin Road to Westcott Road will be closed for approximately five months for sewer, pavement, watermain and streetlighting rehabilitation. Local traffic will be permitted only. The westbound lane of Seminole Street will be shifted around the area of construction at the intersection of Aubin and Seminole as needed.
|
Joe Bressan, EIT Engineering 1, Operations (519) 255-6100 x6890 |
Sterling Ridge Infrastructure Inc. |
Complete |
sewer,road,watermain |
Complete All |
07/18/2022 00:00:00 |
12/23/2022 00:00:00 |
Banwell Road (From Palmetto Street to Mulberry Drive/Wildwood Drive) |
8/2/2022 |
6/30/2023 |
Tuesday, August 02, 2022 to Friday, June 30, 2023 |
Installation of storm sewers, road widening (including trail and sidewalks), roundabout and streetlights on Banwell Road from Palmetto Street to Mulberry Drive/Wildwood Drive. Alternating traffic lanes. Local traffic only.
The southbound lane on Banwell Road between Palmetto Street and Mulberry/Wildwood Drive will be closed on Thursday, September 1 from 9:00am to 3:00pm and on Friday, September 2 from 9:00am to 2:00pm for streetlight work. Local traffic only.
As part of the Banwell Road improvements, Phase 2, the Wildwood Drive/Banwell Road intersection will be closed to traffic for sewer work. From 7:00am to 5:00pm on Monday, October 3 to Thursday, October 6, 2022.
|
Paul Mourad, P. Eng. (519) 255-6100 x6119 |
SheaRock Construction Group Inc. |
Current |
sewer,road,sidewalk |
Current All |
08/02/2022 00:00:00 |
06/30/2023 00:00:00 |
Cabana Corridor Improvements Phase 3 (From Dougall Avenue to Dominion Boulevard) |
6/9/2022 |
12/20/2022 |
Thursday, June 09, 2022 to Tuesday, December 20, 2022 |
Cabana Road West from Dougall Avenue to Dominion Boulevard will have isolated lane restrictions for boulevard restoration and surface asphalt pavement.
|
Jane He, P. Eng., Engineering (519) 255-6257 x6358 |
Amico Infrastructures |
Complete |
road |
Complete All |
06/09/2022 00:00:00 |
12/20/2022 00:00:00 |
Cabana Road Corridor Improvements - Phase 4 (From Mount Carmel Drive to Highway 3) |
4/10/2023 |
12/22/2023 |
Monday, April 10, 2023 to Friday, December 22, 2023 |
Cabana Road West from Mount Carmel Drive to Highway 3 will be under construction for a new storm sewer and isolated sanitary sewer replacements. Road widening to four lanes plus on-road bike lanes with buffer zone, including curb and gutter, sidewalks and street lighting from Dominion Bulevard to Highway 3. Traffic may be intermittently restricted to one lane during the day with flag persons on site. The construction is anticipated to be completed before the end of 2023, weather permitting.
Cabana Road West will be reduced to one lane in each direction between Glenwood Avenue and Charlevoix Avenue as part of Phase 4 of the Cabana Road Corridor Improvements. No left turns will be permitted. Flagging may occur during the construction as needed.
Geraedts Drive, the north side entrance to St. Clair College from Cabana Road, will be closed during road and sewer construction as part of Cabana Road Improvement project - Phase 4. From Monday, May 22, 2023 until the end of June 2023.
All access to the St. Calir College site will be from the Highway 3 entrance during this time. Access to the Sport Plex will be maintained during this time of closure, but access to Lot V will not be available due to the closure of Geraedts Drive.
Please follow the detour signage and drive safely.
|
Jane He, P. Eng., Engineering (519) 255-6257 x6358 |
Amico Infrastructures Inc. |
Current |
curb,road,sewer,sidewalk |
Current All |
04/10/2023 00:00:00 |
12/22/2023 00:00:00 |
Cabana Road West - Phase 4 (From Northway Avenue to Dominion Boulevard) |
6/7/2022 |
12/20/2022 |
Tuesday, June 07, 2022 to Tuesday, December 20, 2022 |
Cabana Road West will have isolated lane restrictions between Northway Avenue and Dominion Boulevard for Enwin Utility Contract and the relocation of hydro lines.
Notice to Homeowner - Cabana Ph 4 - ENWIN.pdf
|
Jane He, P. Eng., Engineering (519) 255-6257 x6358 |
Enwin Utility/Black and McDonald |
Complete |
road |
Complete All |
06/07/2022 00:00:00 |
12/20/2022 00:00:00 |
Campbell Avenue (From Curry Avenue to Totten Street) |
5/9/2023 |
5/10/2023 |
Tuesday, May 09, 2023 to Wednesday, May 10, 2023 |
Southbound Campbell Avenue will have lane restrictions between Curry Avenue and Totten Street for sewer work. Please slow down and use caution in the construction zone. From 8:00am to 5:00pm on Tuesday, May 9 and Wednesday, May 10, 2023. |
Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 |
DanRuss |
Complete |
sewer |
Complete All |
05/09/2023 00:00:00 |
05/10/2023 00:00:00 |
Central Avenue (From Temple Drive to Grand Marais Road) |
4/11/2023 |
7/7/2023 |
Tuesday, April 11, 2023 to Friday, July 07, 2023 |
Central Avenue will be reduced to one lane for approximately three months between Temple Drive and Grand Marais Road for cold milling, asphalt paving and bridge repairs. Local traffic only.
From Tuesday, April 11, until Friday, July 7, 2023 (weather permitting).
|
Charles Hartford Contracts Coordinator Operations (519) 255-6560 x4234 |
GIP Paving |
Current |
road,bridge |
Current All |
04/11/2023 00:00:00 |
07/07/2023 00:00:00 |
Curry Avenue (From Norfolk Street to Richardie Boulevard) |
5/24/2023 |
5/26/2023 |
Wednesday, May 24, 2023 to Friday, May 26, 2023 |
Curry Avenue will be closed between Norfolk Street and Richardie Boulevard for placement of surface asphalt. No street parking from 7:00am to 7:00pm. On Wednesday, May 24 until Friday, May 26, 2023 (weather permitting). |
Charles Hartford Contracts Coordinator Operations (519) 255-6560 x4234 |
GIP Paving |
Complete |
road |
Complete All |
05/24/2023 00:00:00 |
05/26/2023 00:00:00 |
Dominion Boulevard (From Northwood Street to Labelle Street) |
4/11/2022 |
8/3/2022 |
Monday, April 11, 2022 to Wednesday, August 03, 2022 |
Dominion Boulevard North and South Bound, from Northwood Street to Labelle Street will be down to a single lane in both directions for approximately 80 days for bridge rehabilitation.
|
Brian Rempel (519) 255-6560 x4333 |
Coco Paving |
Complete |
bridge |
Complete All |
04/11/2022 00:00:00 |
08/03/2022 00:00:00 |
Dorchester Road (From Huron Church Road to Felix Avenue) |
4/13/2023 |
4/19/2023 |
Thursday, April 13, 2023 to Wednesday, April 19, 2023 |
Dorchester Road will be closed between Huron Church Road and Felix Avnue for road panel placement. On Thursday, April 13 until Wednesday, April 19, 2023. |
Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 |
PieraCon |
Complete |
road |
Complete All |
04/13/2023 00:00:00 |
04/19/2023 00:00:00 |
Dougall Avenue (From Ouellette Avenue to Eugenie Street West) |
8/8/2022 |
12/16/2022 |
Monday, August 08, 2022 to Friday, December 16, 2022 |
Dougall Avenue from Ouellette Avenue to Eugenie Street West will be closed for approximately 3 months for storm sewer, pavement, watermain and street lighting rehabilitation. Local traffic will be permitted only. The southbound lane of Dougall Avenue will be closed during working hours.
|
Patrick Muzyka, P. Eng. Technologist III (519) 255-6100 x6472 |
Sherway Contracting (Windsor) Limited |
Complete |
road,sewer,watermain |
Complete All |
08/08/2022 00:00:00 |
12/16/2022 00:00:00 |
E.C. Row Avenue East (From East of 9455 Anchor Drive to Banwell Road) |
8/25/2022 |
3/31/2023 |
Thursday, August 25, 2022 to Friday, March 31, 2023 |
Temporary Road closure on EC ROW Avenue East between East side of 9455 Anchor Drive and Banwell Road. The closure is due to restore boulevard construction in this area. Proper pedestrian and traffic signs will be present.
|
Patrick Winters, Development Engineer, (519)255-6257 x6462 |
A-BM - Brian Conklin, Senior Project Manager |
Complete |
road |
Complete All |
08/25/2022 00:00:00 |
03/31/2023 00:00:00 |
E.C. Row Expressway (From Huron Church Road to Howard Avenue) |
4/13/2022 |
8/5/2022 |
Wednesday, April 13, 2022 to Friday, August 05, 2022 |
E.C. Row Expressway will have lane restrictions in both directions between Huron Church Road and Howard Avenue for approximately 17 weeks for road reconstruction.
E.C. Row Expressway Eastbound On ramp at Dominion Boulevard and Off ramp at Dougall Avenue will be closed for approximately the next 50 days. From April 28 to July 25 - weather permitting.
E.C. Row Expressway Westbound On ramp at Dougall Avenue will have daily shoulder closures for approximately the next 14 days. May 11 to May 25 - weather permitting.
E.C. Row Expressway Eastbound OFF ramp at Dominion Boulevard will be CLOSED for approximately 4 hours (10:00am - 2:00pm) on Wednesday, May 25 - weather permitting.
|
CJ Hartford Contracts Coordinator Operations (519) 945-9971 x4234 |
Coco Paving |
Complete |
road |
Complete All |
04/13/2022 00:00:00 |
08/05/2022 00:00:00 |
E.C. Row Expressway (From Howard Avenue to Walker Road) |
6/11/2023 |
7/17/2023 |
Sunday, June 11, 2023 to Monday, July 17, 2023 |
The eastbound E.C. Row Expressway will have nightly closures between Howard Avenue and Walker Road for mill-and-pave work. One lane will remain open during daytime hours. Motorists are encouraged to find an alternative route. From 8:00pm to 6:00am Sunday, June 11 until Monday, July 17, 2023. |
CJ Hartford Contracts Coordinator Operations (519) 255-6560 x4234 |
GIP Paving |
Planned |
road |
Planned All |
06/11/2023 00:00:00 |
07/17/2023 00:00:00 |
E.C. Row Expressway On-Ramp (From E.C. Row Expressway to Central Avenue) |
5/24/2023 |
5/24/2023 |
Wednesday, May 24, 2023 |
The Eastbound E.C. Row Expressway on-ramp at Central Avenue will have lane restrictions for guardrail repairs. On Wednesday, May 24, 2023 from 11:00am to 3:00pm |
Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 |
Royal Fence |
Complete |
road |
Complete All |
05/24/2023 00:00:00 |
05/24/2023 00:00:00 |
E.C. Row Expressway Ramp and Lane Closures (From Lauzon Parkway to Jefferson Boulevard) |
3/9/2021 |
3/9/2021 |
Tuesday, March 09, 2021 |
Ramp and Lane closures on E.C. Row Expressway between Jefferson Boulevard and Lauzon Parkway for guardrail repairs will affect traffic flow.
Closure of eastbound on-ramp at Lauzon Parkway, 9 a.m. to 12 p.m.
Closure of eastbound off-ramp at Lauzon Parkway and northbound lane restrictions, 12 p.m. to 2 p.m.
Westbound lane restrictions between Lauzon Parkway and Jefferson Boulevard, 12 p.m. to 3 p.m. |
Michael Cappucci, Contracts Coordinator 519-255-6326 |
Royal Fence |
Complete |
None. |
Complete All |
03/09/2021 00:00:00 |
03/09/2021 00:00:00 |
Ellrose Avenue and Milloy Street (From see description to see description) |
7/21/2022 |
10/31/2022 |
Thursday, July 21, 2022 to Monday, October 31, 2022 |
The Windsor Utilities Commission will be reconstructing the watermains on:
Ellrose Avenue from Milloy Street to Tecumseh Road East (Ward 5)
Milloy Street from Bernard Road to Aurthur Road (Ward 5)
WUC Contract 2022-009 Pre-Construction Letter Ellrose Milloy.pdf
|
Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 |
D'Amore Construction |
Complete |
watermain |
Complete All |
07/21/2022 00:00:00 |
10/31/2022 00:00:00 |
Francois Road (From Alice Street to Tecumseh Road East) |
8/4/2022 |
11/11/2022 |
Thursday, August 04, 2022 to Friday, November 11, 2022 |
The Windsor Utilities Commission will be resonstructing the watermains on:
Francois Road - Alice Street to Tecumseh Road East
WUC Contract 2022-009 Pre-Construction Letter Francois.pdf
|
Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 |
D'Amore Construction |
Complete |
watermain |
Complete All |
08/04/2022 00:00:00 |
11/11/2022 00:00:00 |
George Avenue (From Ontario Street to Tecumseh Road East) |
4/4/2022 |
8/26/2022 |
Monday, April 04, 2022 to Friday, August 26, 2022 |
The Windsor Utilities Commission will be reconstructing the watermains on: George Avenue from Ontario Street to Tecumseh Road East (Ward 5).
WUC Contract 2022-003 Pre-Construction Letter George.pdf
|
Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 |
Major Construction (2010) Ltd. |
Complete |
watermain |
Complete All |
04/04/2022 00:00:00 |
08/26/2022 00:00:00 |
Giles Boulevard East (From Parent Avenue to Gladstone Avenue) |
4/10/2023 |
5/26/2023 |
Monday, April 10, 2023 to Friday, May 26, 2023 |
Giles Boulevard East from Gladstone Avenue to Parent Avenue will resume construction for pavement work on the north side (westbound lane).
Giles Boulevard East will be partially closed. The closure of lanes and intersections will depend on the progress of construction and may/may not permit local traffic and side road parking.
Please follow the detour signage and drive safely.
From April 10, 2023 to May 26, 2023.
|
Aojeen Issac, P. Eng. Engineering Department (519) 255-6257 x6368 |
J.C.S. Construction Inc. / City of Windsor |
Complete |
road |
Complete All |
04/10/2023 00:00:00 |
05/26/2023 00:00:00 |
Giles Boulevard West (From Dougall Avenue to Victoria Avenue) |
5/1/2023 |
5/12/2023 |
Monday, May 01, 2023 to Friday, May 12, 2023 |
Eastbound Giles Boulevard West will have lane restrictions between Dougall Avenue and Victoria Avenue for sidewalk construction. On Monday, May 1 until Friday, May 12, 2023. |
Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 |
PieraCon |
Complete |
sidewalk |
Complete All |
05/01/2023 00:00:00 |
05/12/2023 00:00:00 |
Gladstone Avenue and Seneca Street (From see description to see description) |
6/6/2022 |
8/26/2022 |
Monday, June 06, 2022 to Friday, August 26, 2022 |
The Windsor Utlilties Commission will be reconstructing the watermains on:
Gladstone Avenue from Tecumseh Road East to Seneca Street (Ward 4)
Seneca Street from Gladstone Avenue to Moy Avenue (Ward 4)
City Ops Contract 18-22 Pre-Construction Letter Gladstone Seneca.pdf
|
Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 |
D'Amore Construction |
Complete |
watermain |
Complete All |
06/06/2022 00:00:00 |
08/26/2022 00:00:00 |
Glenwood Pedestrian Bridge Closure (Grand Marais Drain) |
7/25/2022 |
9/30/2022 |
Monday, July 25, 2022 to Friday, September 30, 2022 |
Glenwood Pedestrian Bridge over Grand Marais Drain will be closed for reconstruction. No pedestrian access will be allowed during construction. From Monday, July 25 until Friday, September 30, 2022. |
Phong Nguy Manager of Contracts, Field Services and Maintenance (519) 255-6326 |
Front Construction Industries Inc. |
Complete |
bridge |
Complete All |
07/25/2022 00:00:00 |
09/30/2022 00:00:00 |
Glidden Avenue (From Wyandotte Street East to CNR rail tracks) |
3/2/2022 |
6/10/2022 |
Wednesday, March 02, 2022 to Friday, June 10, 2022 |
The Windsor Utilities Commission will be reconstructing the watermains on Glidden Avenue from Wyandotte Street East to CNR Tracks (Ward 6).
WUC Contract 2021-027 Pre-Construction Letter Glidden.pdf
|
Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 |
D'Amore Construction (2000) Ltd. |
Complete |
watermain |
Complete All |
03/02/2022 00:00:00 |
06/10/2022 00:00:00 |
Goyeau Street/Riverside Drive Intersection (From Riverside Drive East to Goyeau Street) |
4/17/2023 |
4/19/2023 |
Monday, April 17, 2023 to Wednesday, April 19, 2023 |
The intersection of Riverside Drive East and Goyeau Street will have lane restrictions for road panel placement. On Monday, April 17 until Wednesday, April 19, 2023. |
Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 |
PieraCon |
Complete |
road |
Complete All |
04/17/2023 00:00:00 |
04/19/2023 00:00:00 |
Hawthorne Drive (From Roseville Park to Lauzon Road) |
5/11/2022 |
7/25/2022 |
Wednesday, May 11, 2022 to Monday, July 25, 2022 |
Partial lane closures along Hawthorne Drive for the construction of asphalt pathways. Work will primarily take place off the roadway, but lane restrictions may occasionally be required. A flag person will be present when traffic is reduced to one lane of traffic.
|
Juan Paramo, Transportation Planning (519) 999-6378 |
PieraCon |
Complete |
road |
Complete All |
05/11/2022 00:00:00 |
07/25/2022 00:00:00 |
Hawthorne Drive (From Lauzon Parkway to Enterprise Way) |
5/8/2023 |
5/26/2023 |
Monday, May 08, 2023 to Friday, May 26, 2023 |
Hawthorne Drive will be closed between Lauzon Parkway and Enterprise Way for roadwork. Local traffic only. From Monday, May 8 until Friday, May 26, 2023. |
Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 |
PieraCon |
Complete |
road |
Complete All |
05/08/2023 00:00:00 |
05/26/2023 00:00:00 |
Howard Avenue (From South Cameron Boulevard to Kenilworth Drive) |
5/18/2023 |
5/24/2023 |
Thursday, May 18, 2023 to Wednesday, May 24, 2023 |
Aecon Construction will be installing new gas mains along the east and west shoulders of Howard Avenue from South Cameron Boulevard to approximately 160 metres south of Kenilworth Drive.
This work is not anticipated to affect driving lanes but area bus stops will be closed during construction.
On-going to May 24, 2023 - weather permitting. |
Jake Sayer (519) 564-7934 Aecon Construction Group Inc. |
Aecon Construction Group Inc. |
Complete |
road |
Complete All |
05/18/2023 00:00:00 |
05/24/2023 00:00:00 |
Industrial Road (From Huron Church Road to Ambassador Drive) |
6/1/2023 |
6/16/2023 |
Thursday, June 01, 2023 to Friday, June 16, 2023 |
Industrial Road will be closed between Huron Church Road and Ambassador Drive for road repairs. Follow posted detour. On Thursday, June 1 until Friday, June 16, 2023. |
Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 |
PieraCon |
Current |
road |
Current All |
06/01/2023 00:00:00 |
06/16/2023 00:00:00 |
Jos St Louis (From Rose Street to Tecumseh Road East) |
8/8/2022 |
11/4/2022 |
Monday, August 08, 2022 to Friday, November 04, 2022 |
Jos St Louis Avenue from Rose Street to Tecumseh Road East will be closed for approximately 3 months for storm sewer, sanitary sewer , pavement and water services rehabilitation. Local traffic will be permitted only. The southbound traffic on Jos St Louis Avenue will be shifted around the area of construction. There will be temporary lane closures on Tecumseh Road East from Rivard Avenue to Clemenceau Boulevard for approximately one week for sewer work in the Jos St Louis Avenue and Tecumseh Road East intersection.
Curb work at the Jos St. Louis/Tecumseh Road East intersection will result in temporary lane closure on Tecumseh Road East and Rivard Avenue to Clemenceau Boulevard for approximately two days. From Friday, October 28, 2022 until Saturday, October 29, 2022.
|
Patrick Muzyka, P. Eng. Technologist III (519) 255-6100 x6472 |
D'Amore Construction (2000) Ltd. |
Complete |
sewer,road,watermain |
Complete All |
08/08/2022 00:00:00 |
11/04/2022 00:00:00 |
Kildare Road (From Tecumseh Road East to Seneca Street) |
8/8/2022 |
10/28/2022 |
Monday, August 08, 2022 to Friday, October 28, 2022 |
The Windsor Utilities Commission will be reconstructing the watermains on:
Kildare Road - Tecumseh Road East to Seneca Street
City Ops Contract 18-22 Pre-Construction Letter Kildare.pdf
|
Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 |
D'Amore Construction |
Complete |
watermain |
Complete All |
08/08/2022 00:00:00 |
10/28/2022 00:00:00 |
Kildare Road, Ottawa Street, Ontario Street (From see description to see description) |
3/20/2023 |
6/2/2023 |
Monday, March 20, 2023 to Friday, June 02, 2023 |
The Windsor Utilities Commission will be reconstructing the watermains on:
Kildare Road from Richmond Street to Ottawa Street (Ward 4)
Ottawa Street from Windermere Road to Argyle Road (Ward 4)
Ontario Street from Chilver Road to Monmouth Road (Ward 4)
Canada Post - Please be advised there should be minimal disruption to mail routes. Road, driveway and sidewalk replacement will be very limited.
|
Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 |
SheaRock Construction |
Complete |
watermain |
Complete All |
03/20/2023 00:00:00 |
06/02/2023 00:00:00 |
Langlois Avenue (From Giles Boulevard East to Shepherd Street East) |
5/18/2022 |
7/15/2022 |
Wednesday, May 18, 2022 to Friday, July 15, 2022 |
Langlois Avenue is closed between Giles Boulevard East and Shepherd Street East for road and watermain reconstruction. Access for local traffic only. Ongoing until Friday, July 15, 2022. |
Daniel Lopez - Engineer I Public Works Operations (519) 945-9971 |
D'Amore Construction (2000) Ltd. |
Complete |
road,watermain |
Complete All |
05/18/2022 00:00:00 |
07/15/2022 00:00:00 |
Lauzon Parkway (From Twin Oaks Drive to CP Rail Bridge) |
8/22/2022 |
10/1/2022 |
Monday, August 22, 2022 to Saturday, October 01, 2022 |
Lauzon Parkway will have lane restrictions over the CP Rail bridge just south of Twin Oaks Drive for bridge repairs and paving. Please slow down and use caution in the construction zone. |
Charles Hartford Contracts Coordinator Operations (519) 255-6326 x4234 |
Front Construction Industries Inc. |
Complete |
bridge,road |
Complete All |
08/22/2022 00:00:00 |
10/01/2022 00:00:00 |
Lynngrove Crescent, Lynngrove Court and Melville Drive (From see description to see description) |
9/23/2022 |
11/18/2022 |
Friday, September 23, 2022 to Friday, November 18, 2022 |
Lynngrove Crescent, Lynngrove Court and Melville Drive will be closed for approximately seven weeks for curb repairs as well as milling and paving work. Local traffic only. From Friday, September 23 until Friday, November 18, 2022.
|
Daryl Lundy, A.Sc.T., Contracts Supervisor (519) 255-6560 x4330 |
Amico Infrastructures Inc. |
Complete |
curb,road |
Complete All |
09/23/2022 00:00:00 |
11/18/2022 00:00:00 |
Mark Avenue (From Campbell Avenue to Algonquin Street) |
5/24/2023 |
5/26/2023 |
Wednesday, May 24, 2023 to Friday, May 26, 2023 |
Mark Avenue will be closed between Campbell Avenue and Algonquin Street for placement of surface asphalt. No street parking between 7:00am and 7:00pm. On Wednesday, May 24 until Friday, May 26, 2023 (weather permitting). |
Charles Hartford Contracts Coordinator Operations (519) 255-6560 x4234 |
Coco Paving |
Complete |
road |
Complete All |
05/24/2023 00:00:00 |
05/26/2023 00:00:00 |
Matchette Road (From Broadway Street to E.C. Row Expressway) |
9/14/2022 |
11/4/2022 |
Wednesday, September 14, 2022 to Friday, November 04, 2022 |
Matchette Road will have lane narrowing between Broadway Street and the westbound E.C. Row Expressway off-ramp for construction of a multi-use trail. Please watch for pylons and use caution where workers are present.
|
Josie Liburdi Project Coordinator Engineering (519) 255-6100 x6145 |
Sterling Ridge Infrastructure Inc. |
Complete |
road |
Complete All |
09/14/2022 00:00:00 |
11/04/2022 00:00:00 |
Matthew Brady (From St. Rose Avenue to Wyandotte Street East) |
8/29/2022 |
11/30/2022 |
Monday, August 29, 2022 to Wednesday, November 30, 2022 |
Matthew Brady Boulevard from St. Rose Avenue to Wyandotte Street East will be closed for approximately 3 months for storm sewer, sanitary sewer, watermain and pavement rehabilitation. There will be a temporary lane closure of the eastbound lanes on Wyandotte Street East from Eastlawn Avenue to St. Paul Avenue for approximately four weeks, Monday, September 5, 2022 to Friday, September 30, 2022 for sewer work in the Matthew Brady Boulevard and Wyandotte Street Intersection. During this time Wyandotte Street East will be reduced to two lanes, one in each direction.
|
Adam Mourad, P. Eng. (519) 255-6100 x6614 |
Old Castle Contracting Inc. |
Complete |
road,sewer,watermain |
Complete All |
08/29/2022 00:00:00 |
11/30/2022 00:00:00 |
North Talbot Road (From Howard Avenue to Southwood Lakes Boulevard) |
4/11/2022 |
6/17/2022 |
Monday, April 11, 2022 to Friday, June 17, 2022 |
Installation of storm sewers, road widening (including bike lanes and sidewalks) and streetlights on North Talbot Road from Howard Avenue to east of Southwood Lakes Boulevard. Local Traffic only.
|
Paul Mourad, P. Eng. (519) 562-2448 |
SheaRock Construction Group Inc. |
Complete |
sidewalk,road,sewer |
Complete All |
04/11/2022 00:00:00 |
06/17/2022 00:00:00 |
Ojibway Parkway (From Ojibway Parkway to Sprucewood Avenue) |
5/25/2023 |
6/2/2023 |
Thursday, May 25, 2023 to Friday, June 02, 2023 |
The northbound Ojibway Parkway left turn lane to Sprucewood Avenue will be closed for ditch maintenance. From 6:00am to 6:00pm on Thursday, May 25 and Friday, May 26, 2023.
The northbound Ojibway Parkway right turn lane to Sprucewood Avenue will be closed for ditch maintenance. From 8:00am to 5:00pm on Friday, June 2, 2023. |
Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 |
Belmont Inc. |
Complete |
road |
Complete All |
05/25/2023 00:00:00 |
06/02/2023 00:00:00 |
Ottawa Street and Parent Avenue Intersection (From Ottawa Street to Parent Avenue) |
4/3/2023 |
4/14/2023 |
Monday, April 03, 2023 to Friday, April 14, 2023 |
The intersection of Ottawa Street and Parent Avenue will continue to have lane restrictions for westbound and northbound traffic due to sewer repairs. Traffic markers may remain in place over the holiday weekend if work is required to extend into next week. |
Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 |
DanRuss |
Complete |
sewer |
Complete All |
04/03/2023 00:00:00 |
04/14/2023 00:00:00 |
Ouellette Avenue (From Tecumseh Road to Eugenie Street) |
5/1/2023 |
8/23/2023 |
Monday, May 01, 2023 to Wednesday, August 23, 2023 |
Ouellette Avenue will be reduced to one lane in each direction from Tecumseh Road to Eugenie Avenue for road and bridge repair work from May 1, 2023 to August 19, 2023.
|
Zoran Savic, Contracts Supervisor Operations (519) 255-6560 x4231 |
Sterling Ridge Infrastructure Inc. |
Current |
road,bridge |
Current All |
05/01/2023 00:00:00 |
08/23/2023 00:00:00 |
Parkside Court (From Beals Street West to 1548 Parkside Court) |
11/16/2020 |
12/7/2020 |
Monday, November 16, 2020 to Monday, December 07, 2020 |
Parkside Court will be closed from Beals Street West to 1548 Parkside Court for Watermain Reconstruction.
|
Spencer Johnston, WUC 519-251-7300 x 609 |
To be determined.
|
Complete |
watermain |
Complete All |
11/16/2020 00:00:00 |
12/07/2020 00:00:00 |
Provincial Road (From see description to see description) |
3/13/2023 |
11/30/2023 |
Monday, March 13, 2023 to Thursday, November 30, 2023 |
Installation of storm sewer, watermain, concrete road, multi-use trails and streetlights on Provincial Road between South of Cabana Road East to Legacy Park Drive and on Sixth Concession Road from Cabana Road East to CN Rail. Alternating traffic lanes.
Sixth Concession Road from Provincial Road to Cabana Road will be closed for construction on Tuesday, May 23, 2023 at 6:00am until Monday, June 5, 2023 at 8:00pm.
|
Paul Mourad, P. Eng. (519) 255-6100 x6119 |
Green Infrastructure Partners Inc. |
Current |
sewer,road,watermain |
Current All |
03/13/2023 00:00:00 |
11/30/2023 00:00:00 |
Provincial Road and Sixth Concession Road Intersection (From see description to see description) |
5/23/2023 |
6/5/2023 |
Tuesday, May 23, 2023 to Monday, June 05, 2023 |
The Intersection of Sixth Concession and Provincial Road will be closed to through traffic in all directions. Detour will be in place. Starting on Tuesday, May 23, 2023 from 6:00am to 8:00pm, until Monday, June 5, 2023. |
Paul Mourad, P. Eng. (519) 255-6100 x6119 |
Green Infrastructure Partners Inc. |
Complete |
road |
Complete All |
05/23/2023 00:00:00 |
06/05/2023 00:00:00 |
Riberdy Road (From EC Row to Foster Ave) |
7/4/2022 |
9/23/2022 |
Monday, July 04, 2022 to Friday, September 23, 2022 |
The Windsor Utilities Commission will be reconstructing the watermains on:
Riberdy Road from EC Row to Foster Ave.
WUC Contract 2022-014 Pre-Construction Letter Riberdy.pdf
|
Spencer Johnston, Manager Water Construction & Design (519)251-7300 x609 |
SheaRock Construction |
Complete |
watermain |
Complete All |
07/04/2022 00:00:00 |
09/23/2022 00:00:00 |
Riverside Drive East (From Patrice Drive to St. Rose Avenue) |
5/16/2023 |
5/17/2023 |
Tuesday, May 16, 2023 to Wednesday, May 17, 2023 |
Eastbound Riverside Drive East will have lane restrictions between Patrice Drive and St. Rose Avenue for sewer work. Please slow down and use caution in the construction zone. From 7:00am to 6:00pm on Tuesday, May 16 and Wednesday, May 17, 2023. |
Adam Mourad, P. Eng. (519) 255-6100 x6614 |
DanRuss Contracting Inc. |
Complete |
sewer |
Complete All |
05/16/2023 00:00:00 |
05/17/2023 00:00:00 |
Rooney Street/Josephine Avenue (From see description to see description) |
5/10/2022 |
8/16/2022 |
Tuesday, May 10, 2022 to Tuesday, August 16, 2022 |
Rooney Street will be closed from Campbell Avenue to Partington Avenue and Josephine Avenue will be closed from Rooney Street to Wyandotte Street West for road and watermain reconstruction. Local traffic only. |
Daniel Lopez - Engineer I Public Works Operations (519) 945-9971 |
J.C.S. Construction Inc. |
Complete |
road,watermain |
Complete All |
05/10/2022 00:00:00 |
08/16/2022 00:00:00 |
Sandwich Street (From Ojibway Parkway to Chappell Avenue) |
11/7/2022 |
12/30/2022 |
Monday, November 07, 2022 to Friday, December 30, 2022 |
The Windsor Utilities Commission will be reconstructing the watermains on Sandwich Street from Ojibway Parkway to Chappell Avenue (Ward 1 and 2)
WUC Contract 2022-015 Pre-Construction Letter Sandwich.pdf |
Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 |
SheaRock Construction Group Inc. |
Complete |
watermain |
Complete All |
11/07/2022 00:00:00 |
12/30/2022 00:00:00 |
St. Luke Road and Reginald Street (From see description to see description) |
3/13/2023 |
9/1/2023 |
Monday, March 13, 2023 to Friday, September 01, 2023 |
St. Luke Road from Alice Street to Seminole Street and Reginald Street from St. Luke Road to Albert Road will have Sanitary and Storm Sewer, Watermain and Pavement Rehabilitation.
Closure of Seminole Street and St. Luke Road Intersection on Monday, March 20 until Friday, March 31, 2023 for sanitary and storm sewer, watermain and pavement rehabilitation.
|
Sarah Meneses, P. Eng. (519) 255-6100 x6336 |
D'Amore Construction (2000) Ltd. |
Current |
sewer,watermain,road |
Current All |
03/13/2023 00:00:00 |
09/01/2023 00:00:00 |
Tecumseh Road East (From Forest Glade Drive to Clover Avenue) |
3/10/2021 8:00 AM |
3/11/2021 5:00 PM |
Wednesday, March 10, 2021 8:00 AM to Thursday, March 11, 2021 5:00 PM |
Tecumseh Road East currently has eastbound lane restrictions between Forest Glade and Clover Avenue for catch basin repairs. |
Roberta Harrison, Maintinance Corrdinator, (519) 266-65660 x4241 |
DanRuss |
Complete |
sewer |
Complete All |
03/10/2021 08:00:00 |
03/11/2021 17:00:00 |
Tecumseh Road East (From Marentette Avenue to Elsmere Avenue) |
5/2/2023 |
5/3/2023 |
Tuesday, May 02, 2023 to Wednesday, May 03, 2023 |
Westbound Tecumseh Road East will have lane restrictions between Marentette Avenue and Elsmere Avenue for sewer repairs. Please slow down and use caution in the construction zone. From 8:00am to 4:00pm on Tuesday, May 2 and Wednesday, May 3, 2023. |
Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 |
DanRuss |
Complete |
sewer |
Complete All |
05/02/2023 00:00:00 |
05/03/2023 00:00:00 |
Tecumseh Road East (From Central Avenue to Drouillard Road) |
5/23/2023 |
5/29/2023 |
Tuesday, May 23, 2023 to Monday, May 29, 2023 |
Westbound Tecumseh Road East will have lane restrictions for sidewalk replacement between Central Avenue and Drouillard Road. On May 23, 2023 until May 29, 2023. |
Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 |
Giorgi Construction |
Complete |
sidewalk |
Complete All |
05/23/2023 00:00:00 |
05/29/2023 00:00:00 |
Tecumseh Road East (From Cadillac Street to Chandler Road) |
5/23/2023 |
5/29/2023 |
Tuesday, May 23, 2023 to Monday, May 29, 2023 |
Eastbound Tecumseh Road East will have lane restrictions for sidewalk repairs between Cadillac Street and Chandler Road. On May 23, 2023 until May 29, 2023. |
Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 |
Giorgi Construction |
Complete |
sidewalk |
Complete All |
05/23/2023 00:00:00 |
05/29/2023 00:00:00 |
Tourangeau Road (From Milloy Street to Tecumseh Road East) |
5/16/2022 |
8/5/2022 |
Monday, May 16, 2022 to Friday, August 05, 2022 |
The Windsor Utilities Commission will be reconstructing the watermains on:
Tourangeau Road from Milloy Street to Tecumseh Road East (Ward 5).
WUC Contract 2022-003 Pre-Construction Letter Tourangeau.pdf
|
Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 |
Major Construction (2010) Ltd. |
Complete |
watermain |
Complete All |
05/16/2022 00:00:00 |
08/05/2022 00:00:00 |
Turner Road, Byng Road, EC Row Avenue (From see description to see description) |
5/23/2022 |
8/12/2022 |
Monday, May 23, 2022 to Friday, August 12, 2022 |
The Windsor Utilities Commission will be reconstructing the watermains on:
Turner Road - EC Row Avenue to Sydney Avenue (Ward 9)
Byng Road - EC Row Avenue to Sydney Avenue (Ward 9)
EC Row Avenue - Byng Road to Walker Road (Ward 9)
WUC Contract 2022-014 Pre-Construction Letter TBE.pdf |
Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 |
Sherway Construction |
Complete |
watermain |
Complete All |
05/23/2022 00:00:00 |
08/12/2022 00:00:00 |
Villaire Avenue, St Louis Avenue and Reedmere Road (From see description to see description) |
2/6/2023 |
3/31/2023 |
Monday, February 06, 2023 to Friday, March 31, 2023 |
The Windsor Utilities Commission will be reconstructing the watermains on:
Villaire Avenue from Wyandotte Street East to Riverside Drive East (Ward 6)
St Louis Avenue from Wyandotte Street East to Riverside Drive East (Ward 6)
Reedmere Road from Wyandotte Street East to Riverside Drive East (Ward 6)
The start date has been set for the week of February 6th weather permitting. Please be advised there should be minimal disruption to mail routes. Road and driveway and sidewalk replacement will be very limited.
WUC Contract 2022-056 Pre Letter VSR.pdf
|
Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 |
SheaRock Construction |
Complete |
watermain |
Complete All |
02/06/2023 00:00:00 |
03/31/2023 00:00:00 |
Walker Road (From Wyandotte Street East to Richmond Street) |
5/4/2023 |
5/4/2023 |
Thursday, May 04, 2023 |
Walker Road between Wyandotte Street East and Richmond Street will have lane restrictions in both directions for road repair. On Thursday, May 4, 2023 from 7:30am to 5:00pm. |
Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 |
Diponti Paving |
Complete |
road |
Complete All |
05/04/2023 00:00:00 |
05/04/2023 00:00:00 |
Walker Road, Ontario Street, Montreuil Avenue, Edna Street (From see description to see description) |
5/8/2023 |
8/11/2023 |
Monday, May 08, 2023 to Friday, August 11, 2023 |
As part of an ongoing infrastructure renewal program, the Windsor Utilities Commission (WUC) will be installing a new 200mm PVC watermain on Ontario Street from Monmouth Road to Walker Road and on Edna Street from Montreuil Avenue to St. Luke Road, as well as a new 300 PVC watermain on Walker Road from Richmond Street to Ontario Street and on Montreuil Avenue from Wyandotte Street East to Edna Street as well as a new 400mm PVC watermain on Walker Road from Tuscarora Street to Richmond Street.
|
Spencer Johnston, Manager Water Construction & Design (519) 251-7300 x609 |
SheaRock Construction |
Current |
watermain |
Current All |
05/08/2023 00:00:00 |
08/11/2023 00:00:00 |
Wellesley Avenue (From see description to see description) |
4/10/2023 |
9/1/2023 |
Monday, April 10, 2023 to Friday, September 01, 2023 |
Wellesley Avenue will be closed between Terminal Street and Ypres Avenue for a sewer and pavement rehabilitation. Local traffic only.
Vimy Avenue will be closed between Wellesley Avenue and Forest Avenue. No through traffic, detour signs will be in place.
From Monday, April 10, 2023 to Friday, September 1, 2023 (weather permitting)
The intersection of Wellesley Avenue and Terminal Street will be closed for road work on Thursday, June 1, 2023 from 7:00am to 6:00pm.
|
Pierfrancesco Ruggeri, C.E.T. Technologist III 519-255-6257 x6506 |
GIP Paving Inc. |
Current |
sewer,road |
Current All |
04/10/2023 00:00:00 |
09/01/2023 00:00:00 |
Westminster Boulevard (From Tecumseh Road East to Adstoll Avenue) |
4/5/2022 |
6/30/2022 |
Tuesday, April 05, 2022 to Thursday, June 30, 2022 |
Westminster Boulevard, Tecumseh Road East to Adstoll Avenue will be closed for approximately 3 months for road and watermain reconstruction. Local traffic will be permitted only.
|
Daryl Lundy, A.Sc.T., Contracts Supervisor (519) 255-6560 x4330 |
JCS |
Complete |
road,watermain |
Complete All |
04/05/2022 00:00:00 |
06/30/2022 00:00:00 |
Wyandotte Street East (From Watson Avenue to Isack Avenue) |
4/10/2023 |
5/5/2023 |
Monday, April 10, 2023 to Friday, May 05, 2023 |
Wyandotte Street East from Watson Avenue to Isack Avenue will have lane closures for the construction of a lane widening. There will be periods of time that access to driveways will be limited during construction, the contractor will make every effort to keep inconveniences to a minimum.
Construction is scheduled to begin on the week of April 10, 2023 with an estimated completion date of May 2023.
|
Shannon Mills, Technologist III - Engineering 519-255-6257 x6635 |
SheaRock Construction Group Inc. |
Complete |
road |
Complete All |
04/10/2023 00:00:00 |
05/05/2023 00:00:00 |
Wyandotte Street East (From Victor Drive to Patrice Drive) |
4/20/2023 |
4/28/2023 |
Thursday, April 20, 2023 to Friday, April 28, 2023 |
Eastbound Wyandotte Street East will have intermitten lane restrictions between Victor Drive and Patrice Drive for sidewalk repairs. From Thursday, April 20 until Friday, April 28, 2023. |
Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 |
Giorgi Construction |
Complete |
sidewalk |
Complete All |
04/20/2023 00:00:00 |
04/28/2023 00:00:00 |
Wyandotte Street East (From Reedmere Road to Esdras Avenue) |
4/24/2023 |
4/28/2023 |
Monday, April 24, 2023 to Friday, April 28, 2023 |
Wyandotte Street East will have curb lane restrictions in both directions between Reedmere Road and Esdras Avenue for sewer repair. Please slow down and use caution in the construction zone. From Monday, April 25 until Friday, April 28, 2023. |
Roberta Harrison, Maintenance Coordinator (519) 255-6560 x4241 |
DanRuss Paving |
Complete |
sewer |
Complete All |
04/24/2023 00:00:00 |
04/28/2023 00:00:00 |